INSP-Final Inspection | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/10/2007 | 5/10/2007 | 5/10/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need permanant heat installed in building for the fire sprinkler system. All other items are ok. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2007 | 5/8/2007 | 5/8/2007 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Supply line flush | 10/26/2006 | 10/27/2006 | 10/27/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/29/2006 | 9/29/2006 | 9/29/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 9/7/2006 | 9/8/2006 | 9/8/2006 | A | PASS |
Troy Cobbley
|
|
|
The remaining underground is ok for cover
|
INSP-Sprinkler Rough-in | 8/29/2006 | 8/29/2006 | 8/29/2006 | P | PART |
Troy Cobbley
|
|
|
Underground supply piping from the united water connection to the first 90 is ok to cover. The first 90 and the thrust block has not been installed yet.
|