INSP-Final Inspection | 2/14/2007 | 2/15/2007 | 2/16/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2007 | 1/12/2007 | 1/12/2007 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | FAIL |
Troy Cobbley
|
|
|
Could not get access into the building. Tried twice.
|
INSP-Sprinkler Rough-in | 12/13/2006 | 12/14/2006 | 12/14/2006 | A | PART |
Troy Cobbley
|
|
|
Piping is ok to cover. One attic pendant head has not been installed and the attic pendant heads install on the 4" main at the riser are too far from the insulation. See city approved plans for locations. Contractor states access will be provided to verify these items later.
|
INSP-Sprinkler Rough-in | 12/6/2006 | 12/7/2006 | 12/7/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover in the permited tenant areas only. The areas that have no tenant build outs at this time still need rough-in inspections
|
INSP-Sprinkler Rough-in | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PART |
Troy Cobbley
|
|
|
The sprinkler piping in 13905, morris dentist is ok to cover
|