INSP-Final Inspection | 12/18/2006 | 12/22/2006 | 12/22/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PART |
Forrest France
|
|
|
Completed main tie-in, branch line tie-ins, final pending completion of the ceiling at one location and final walk through of cleanroom/plemum areas.
|
INSP-Final Inspection | 11/17/2006 | 11/21/2006 | 11/21/2006 | A | CANC |
Forrest France
|
|
|
Final sprinkler inspection for RDA remodel.; Phone #: ###-#### Internet Inspection Request from: Greg Kirkes Inspection cancelled from web by: Greg Kirkes
|
INSP-Sprinkler Rough-in | 11/8/2006 | 11/13/2006 | 11/13/2006 | A | PART |
Forrest France
|
|
|
OH rough-in is okay to cover except at the main and branch line tie in locations, two drops are not complete, underfloor sprinklers are acceptable.
|