INSP-Final Inspection | 5/1/2007 | 5/1/2007 | 5/1/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 4/23/2007 | 4/24/2007 | 4/24/2007 | A | FAIL |
Forrest France
|
|
|
Noted several items in need of correction prior to final including painted heads at various locations, missing flex couplings at the standipe risers in the stairwells, mixed head types in the south stairway, missing escutcheons at some locations, leaking head at the model unit bathroom, forward flow completed okay, missing automatic ball drip at the FDC check, need to test AFS monitoring as well.
|
INSP-Sprinkler Rough-in/Hydro | 3/16/2007 | 3/19/2007 | 3/19/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic test of the OH main and standpipes completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 3/6/2007 | 3/6/2007 | 3/6/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test for the basement level parking garage system and the 1st level garage access ramp fire sprinkler piping completed okay.
|
INSP-Sprinkler Rough-in/Hydro | 1/2/2007 | 1/3/2007 | 1/3/2007 | A | PART |
Forrest France
|
|
|
AG hydrostatic test for the garage area first level passed.
|
INSP-Supply line flush | 12/29/2006 | 1/2/2007 | 1/2/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 11/27/2006 | 11/28/2006 | 11/28/2006 | A | PART |
Forrest France
|
|
|
Corrections for the 2nd floor rough-in are complete, overhead sprinkler is approved for cover.
|
INSP-Sprinkler Rough-in | 11/27/2006 | 11/27/2006 | 11/27/2006 | P | FAIL |
Forrest France
|
|
|
2nd floor OH sprinkler install needs correction in some areas as indicated on approved plan set including locations where heads are spaced too close, hangers are missing, one head needs to be removed, the sw heads at the patio areas are not yet installed. The 1st floor overhead install at the apartments only is approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PART |
Forrest France
|
|
|
1st floor hydro test okay.
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | PART |
Forrest France
|
|
|
AG hydrostatic test of the 2nd floor passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2006 | 11/20/2006 | 11/20/2006 | A | FAIL |
Forrest France
|
|
|
AG hydrostatic test not ready at this time due to system leakage to be repaired today per contractor.
|
INSP-Sprinkler Rough-in | 11/16/2006 | 11/16/2006 | 11/17/2006 | P | PART |
Forrest France
|
|
|
Need to provide correct as-builts reflecting actual installation of overhead piping for the 3rd floor previous to approval for cover.
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2006 | 11/15/2006 | 11/14/2006 | A | PASS |
Forrest France
|
|
|
OH hydrostatic test of the 3rd floor is acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 11/9/2006 | 11/13/2006 | 11/13/2006 | A | NR |
Forrest France
|
|
|
OH hydrostatic test of the 3rd floor is not ready. 1st floor rough-in of the model unit for cover is okay. Discussed DSW locations at the 3rd floor canopies.
|
INSP-Sprinkler Rough-in | 11/3/2006 | 11/3/2006 | 11/3/2006 | P | PART |
Forrest France
|
|
|
The 5th and 4th floors are approved for cover as noted on job shack plan set.
|
INSP-Sprinkler Rough-in/Hydro | 10/27/2006 | 10/30/2006 | 10/30/2006 | A | PART |
Forrest France
|
|
|
OH hydrostatic test for the 4th floor passed, items noted on previous c/n for the 4th floor have been completed.
|
INSP-Sprinkler Rough-in | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | PART |
Forrest France
|
|
|
OH rough-in inspection for the 4th floor completed today. Noted elevator and garbage chute piping to heads at these locations is not yet complete, one W.D closet needs is missing a SW head, one pendent in a mec. closet is too close to the wall and blocked by ductwork, the provided as-built plans match the installation except as annotated.
|
INSP-Sprinkler Rough-in | 10/16/2006 | 10/16/2006 | 10/16/2006 | P | FAIL |
Forrest France
|
|
|
Inspection for the 5th floor rough-in only, one head as installed is overspaced as marked on approved plans, need to provide documentation that roofing insulation is sufficient to provide adequate freeze protection for overhead piping run in the joist channels at the deck, will need plan review verification that unsprinklered water closets are acceptable for this NFPA 13 system, overhead hydro for the 5th floor is okay, some field modifications have been made which deviate from the approved set of drawings.
|