INSP-Final Inspection | 11/24/2006 | 11/24/2006 | 11/24/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Final Inspection | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | FAIL |
Troy Cobbley
|
|
|
relocate bell to the fdc location
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | PASS |
Troy Cobbley
|
|
|
Above ground hyro test pased on the third try. Unable to start alarm test.
|
INSP-Sprinkler Rough-in | 11/7/2006 | 11/7/2006 | 11/7/2006 | P | PART |
Forrest France
|
|
|
Inspection for a portion of the drop ceiling areas at the main seating area and the kitchen prep. hallway are okay for cover, several pendent heads at scattered locations are not yet installed.
|
INSP-Sprinkler Rough-in | 10/26/2006 | 10/26/2006 | 10/26/2006 | P | PART |
Forrest France
|
|
|
OH rough-in is okay to cover at the hard lid ceilings. Heads in the drop ceilings, UG supply and the riser are not completed.
|
INSP-Sprinkler Rough-in | 10/23/2006 | 10/23/2006 | 10/23/2006 | P | PART |
Forrest France
|
|
|
Partial inspection for the OH rough-in due to several areas not completed, missing EQ bracing at the end main, FDC and top of riser, drops are not installed at some locations, main and branch line installation is acceptable, noted areas at columns and soffits which may present obstructions, 130ft2 spacing to be verified when heads are cut in, UG supply and riser are not completed at this time.
|