Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00744
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 10433 W EMERALD ST
Project NameEmerald Tech Building # 12
Customer Number 
ePlanReview 
Description
Emerald Building #12 - Shell) - To construct a new 12,192 ft/2, one story, office shell building and related site improvements. This building will be constructed of concrete tilt-up exterior walls, concrete slab floor and steel structural columns and roof joists with metal roof deck. This is a shell permit only and separate tenant improvement permits will be required to finish this building for occupancy. The sprinkler scope of work includes installing a wet pipe sprinkler system through out a new 12,192-ft/2, Type V-B office building. A separate permit # FIR06-00618 has been issued for the underground piping. The fire sprinkler overhead work shall comply with NFPA 13-2002, IFC-2003, and the attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD06-01810.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/16/200710/17/200710/17/2007APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection9/10/20079/10/20079/11/2007PFAIL
DetailsTroy Cobbley
No permanant heat has been provided because the gas meter has not been set up. Can not final the permit.
INSP-Final Inspection5/10/20075/10/20075/10/2007PFAIL
DetailsTroy Cobbley
Need permanant heat installed in building for the fire sprinkler system. All other items are ok. Forward flush passed.
INSP-Final Inspection5/8/20075/9/20075/9/2007ACANC
DetailsTroy Cobbley
Fire alarm contractor was not ready for inspection
INSP-Sprinkler Rough-in/Hydro5/8/20075/9/20075/9/2007ACANC
DetailsTroy Cobbley
Fire alarm contractor was not ready for inspection
INSP-Sprinkler Rough-in/Hydro5/7/20075/8/20075/8/2007AFAIL
DetailsTroy Cobbley
Above ground hydro test failed
FIR-Aging Inspection1/24/20071/24/20071/26/2007 NR
DetailsTroy Cobbley
work is in progress