INSP-Final Inspection | 3/27/2007 | 3/29/2007 | 3/30/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final inspection.
|
INSP-Final Inspection | 3/14/2007 | 3/16/2007 | 3/16/2007 | A | DEFR |
Forrest France
|
|
|
Rescheduled due to FAB conditions.
|
INSP-Sprinkler Rough-in/Hydro | 3/12/2007 | 3/13/2007 | 3/13/2007 | A | PART |
Forrest France
|
|
|
OH fire sprinkler inspection for the remainder of the cleanroom expansion and lab room 105 completed. Note, rough-in inspections to be requested and finished prior to ceiling cover. Two heads in the corridor shown to be added are not yet installed.
|
INSP-Conference | 12/7/2006 | 12/8/2006 | 12/8/2006 | A | PART |
Forrest France
|
|
|
Inspection for a portion of the OH fire sprinkler installation as marked on plans is approved for cover.
|