INSP-Final Inspection | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/16/2007 | 1/18/2007 | 1/19/2007 | P | PASS |
Troy Cobbley
|
|
|
forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2007 | 1/16/2007 | 1/16/2007 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | PART |
Troy Cobbley
|
|
|
The sprinkler rough-in matches the plans for the most part. The fire sprinkler contractor added 12 sprinkler heads due to lack of coverage caused by full height walls. Two of the added heads are in the remote area. Plans will need to be resubmitted as well as hydraulic calculations prior to the project being finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2006 | 12/12/2006 | 12/12/2006 | P | FAIL |
Troy Cobbley
|
|
|
No approved overhead sprinkler plans on site. No inspection performed.
|