INSP-Final Inspection | 11/28/2007 | 11/28/2007 | 11/28/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler passed final inspection.
|
INSP-Final Inspection | 11/13/2007 | 11/14/2007 | 11/15/2007 | A | FAIL |
Forrest France
|
|
|
Due to improperly spaced and blocked heads at several locations.
|
INSP-Final Inspection | 11/12/2007 | 11/13/2007 | 11/13/2007 | P | CANC |
Forrest France
|
|
|
Mike B is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
INSP-Final Inspection | 8/30/2007 | 8/31/2007 | 8/31/2007 | P | NR |
Forrest France
|
|
|
Missing as-built plans for verification of field mods.
|
INSP-Final Inspection | 8/23/2007 | 8/27/2007 | 8/27/2007 | A | PART |
Forrest France
|
|
|
Tested riser alarm and supervisory conditions, need to adjust the PIV switch, forward flow completed, project is not ready for final due to missing ceilings at several locations.
|
INSP-Sprinkler Rough-in/Hydro | 7/12/2007 | 7/13/2007 | 7/13/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing passed inspection.
|
INSP-Sprinkler Rough-in | 7/5/2007 | 7/9/2007 | 7/9/2007 | P | FAIL |
Forrest France
|
|
|
Inspection for the 3rd floor fan deck OH rough-in, see approved plan set for red lines.
|
INSP-Sprinkler Rough-in | 7/3/2007 | 7/5/2007 | 7/5/2007 | A | FAIL |
Forrest France
|
|
|
Inspection intended for FIR07-00205, inspected areas C and D on the 2nd level, see sheet FP8 for defficiencies including overspaced heads and blocked heads.
|
INSP-Sprinkler Rough-in | 7/2/2007 | 7/3/2007 | 7/3/2007 | P | CANC |
Forrest France
|
|
|
Rescheduled.
|
INSP-Sprinkler Rough-in | 6/25/2007 | 6/26/2007 | 6/26/2007 | P | PART |
Forrest France
|
|
|
Verified corrections have been made for the basement level piping, noted two stair enclosures are not yet piped, some upright heads in the corridor may become blocked due to excessive amounts of mechanical and electrical equipment in process of installation below the heads.
|
INSP-Sprinkler Rough-in | 6/21/2007 | 6/22/2007 | 6/22/2007 | A | FAIL |
Forrest France
|
|
|
Plans do not match install.
|
FIR-Aging Inspection | 5/31/2007 | 5/31/2007 | 6/1/2007 | | DEFR |
Forrest France
|
|
|
Work in progress, building under construction.
|