Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00940
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10136 S FEDERAL WAY
Project NameMICRON NANOFAB
Customer Number 
ePlanReview 
Description
Add protection to the new Subfab, Scrubber, Process, Reactive and associated areas. These areas will be supplied from a new riser located with in the Fire Riser Room 001K.
This permit is attached to BLD06-02667. The Under Ground work was done under permit # FIR06-00844. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/28/200711/28/200711/28/2007PPASS
DetailsForrest France
Fire sprinkler passed final inspection.
INSP-Final Inspection11/13/200711/14/200711/15/2007AFAIL
DetailsForrest France
Due to improperly spaced and blocked heads at several locations.
INSP-Final Inspection11/12/200711/13/200711/13/2007PCANC
DetailsForrest France
Mike B is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
INSP-Final Inspection8/30/20078/31/20078/31/2007PNR
DetailsForrest France
Missing as-built plans for verification of field mods.
INSP-Final Inspection8/23/20078/27/20078/27/2007APART
DetailsForrest France
Tested riser alarm and supervisory conditions, need to adjust the PIV switch, forward flow completed, project is not ready for final due to missing ceilings at several locations.
INSP-Sprinkler Rough-in/Hydro7/12/20077/13/20077/13/2007APART
DetailsForrest France
OH hydrostatic testing passed inspection.
INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007PFAIL
DetailsForrest France
Inspection for the 3rd floor fan deck OH rough-in, see approved plan set for red lines.
INSP-Sprinkler Rough-in7/3/20077/5/20077/5/2007AFAIL
DetailsForrest France
Inspection intended for FIR07-00205, inspected areas C and D on the 2nd level, see sheet FP8 for defficiencies including overspaced heads and blocked heads.
INSP-Sprinkler Rough-in7/2/20077/3/20077/3/2007PCANC
DetailsForrest France
Rescheduled.
INSP-Sprinkler Rough-in6/25/20076/26/20076/26/2007PPART
DetailsForrest France
Verified corrections have been made for the basement level piping, noted two stair enclosures are not yet piped, some upright heads in the corridor may become blocked due to excessive amounts of mechanical and electrical equipment in process of installation below the heads.
INSP-Sprinkler Rough-in6/21/20076/22/20076/22/2007AFAIL
DetailsForrest France
Plans do not match install.
FIR-Aging Inspection5/31/20075/31/20076/1/2007 DEFR
DetailsForrest France
Work in progress, building under construction.