INSP-Final Inspection | 2/28/2007 | 3/1/2007 | 3/1/2007 | A | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 2/16/2007 | 2/20/2007 | 2/20/2007 | A | PART |
Troy Cobbley
|
|
|
All items on the correction notice have been corrected except the alarm interconnections need verified.
|
INSP-Final Inspection | 1/25/2007 | 1/26/2007 | 1/26/2007 | A | FAIL |
Forrest France
|
|
|
Missing head in the riser room, heads at the storage room are overspaced, one head in the NW hall is overspcaed off an adjacent wall, missing hanger on the hallway 1 1/2 grid main, provide sufficient coverage under the stairs at the east side as discussed. The fire sprinklers in the drop ceiling areas are okay for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2007 | 1/23/2007 | 1/23/2007 | A | PASS |
Troy Cobbley
|
|
|
The above ground hydro test was witnessed by Greg Bolton, the general contractor. System held 204 lbs for 2 hours. He agreed to sign the test papers. These test papers with his signature will be provided to the fire inspector at the next inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/19/2007 | 1/22/2007 | 1/22/2007 | P | CANC |
Forrest France
|
|
|
Overbooked, no time available to complete this inspection today. Notified contact to reschedule per phone conversation.
|
INSP-Sprinkler Rough-in/Hydro | 1/19/2007 | 1/22/2007 | 1/19/2007 | A | CANC |
Forrest France
|
|
|
Bret; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt Inspection cancelled from web by: Victoria Beall
|