Permit Information
Permit NumberFIR06-00954
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 1010 W JEFFERSON ST (BASEMENT)
Project Name1010 JEFFERSON LLC BLDG
Customer Number 
ePlanReview 
Description
The scope included replacing 44 SSP and adding 6 other SSP heads to accommodate a new wall and ceiling layout as a result of tenant improvements. The existing riser assembly will be completely modified to include a new 2.5” back flow device and wall post indicating control valve. All seismic bracing shall be verified under this permit.
When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
This work is attached to permit # BLD06-02655
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/28/20073/1/20073/1/2007APASS
DetailsForrest France
Final fire sprinkler inspection passed, permit finaled.
INSP-Final Inspection2/16/20072/20/20072/20/2007APART
DetailsTroy Cobbley
All items on the correction notice have been corrected except the alarm interconnections need verified.
INSP-Final Inspection1/25/20071/26/20071/26/2007AFAIL
DetailsForrest France
Missing head in the riser room, heads at the storage room are overspaced, one head in the NW hall is overspcaed off an adjacent wall, missing hanger on the hallway 1 1/2 grid main, provide sufficient coverage under the stairs at the east side as discussed. The fire sprinklers in the drop ceiling areas are okay for cover.
INSP-Sprinkler Rough-in/Hydro1/22/20071/23/20071/23/2007APASS
DetailsTroy Cobbley
The above ground hydro test was witnessed by Greg Bolton, the general contractor. System held 204 lbs for 2 hours. He agreed to sign the test papers. These test papers with his signature will be provided to the fire inspector at the next inspection.
INSP-Sprinkler Rough-in/Hydro1/19/20071/22/20071/22/2007PCANC
DetailsForrest France
Overbooked, no time available to complete this inspection today. Notified contact to reschedule per phone conversation.
INSP-Sprinkler Rough-in/Hydro1/19/20071/22/20071/19/2007ACANC
DetailsForrest France
Bret; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt Inspection cancelled from web by: Victoria Beall