Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR06-00967
StatusFinaled
Name NORTHWEST SALES COMPANY
Site Address 101 S CAPITOL BLVD Unit: 600
Project NameUS BANK-6TH FLR
Customer Number 
ePlanReview 
Description
This permit is to remove a few existing audible visual notification appliances and relocate or add as necessary to accommodate the new tenant improvement project for this floor. Building permit # BLD06-02994 is to expand a tenant space located on the 6th story of the US Bank Plaza by about 1,595 square feet. After the expansion, this tenant space will have a total floor area of about 4,263 square feet. The adjacent reduced tenant space will have a floor area of about 5,456 square feet. These spaces are located on the 6th story (14,600 square feet total) of an existing high rise building. The building "core" on this story has a floor area of about 2,670 square feet. Work is to include interior nonbearing walls, interior doors, interior windows, millwork, finishes, and alterations to a suspended ceiling. The fire sprinkler system, fire alarm system, and high-rise life safety systems (and the infrastructure supporting these systems) for the 6th story are required to comply with the provisions of the 2000 IBC. These existing systems, including the installation of quick-response fire sprinkler heads, were required to be upgraded in conjunction with permit BLD03-00539. The restrooms were also required to be upgraded to be accessible to the disabled under that permit. If not already existing, fire-safing shall be installed at the perimeter of the 6th story between the floor and the spandrel glass. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/2/20073/5/20073/6/2007PPASS
DetailsForrest France
Strobe sync repaired while on site, fire alarm final field inspection passed.
INSP-Final Inspection3/1/20073/2/20073/2/2007PCANC
DetailsForrest France
AFTER 2:30, let me know when you can be there... Phone #: ###-#### Inspection cancelled from web by: Rick Groom
INSP-Final Inspection3/1/20073/1/20073/1/2007PNR
DetailsForrest France
Alarm testing not completed due to tenant and inspection scheduling conflict, to be rescheduled for Monday 3/5 pm as agreed.
INSP-Alarm Testing1/4/20071/5/20071/8/2007PPART
DetailsTroy Cobbley
The only area of the fire alarm inspected and passed was the south half. This has been marked on the city approved drawings. The address as listed on the plans is not what is actual. Sam is going to work this out with addressing.