INSP-Final Inspection | 3/8/2007 | 3/8/2007 | 3/8/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2007 | 2/12/2007 | 2/12/2007 | P | PASS |
Troy Cobbley
|
|
|
Hydro tests on the 4" riser, 3" riser and the FDC passed
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2007 | 1/31/2007 | 1/31/2007 | A | PART |
Troy Cobbley
|
|
|
24 hour air test started at 8:45 with 41 psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2007 | 1/24/2007 | 1/24/2007 | A | PART |
Forrest France
|
|
|
The dry system installation at the west portion of building B is approved for cover, also noted c/n items at the east wing dry system building B have been finished.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need additional sprinkler coverage in the southeast corner of the attic and the sway bracing installed on the 2" main. Also the 2x4 trapeze bracing can not be used for the 4" main. This inspection was for the south wing only.
|
INSP-Sprinkler Rough-in/Hydro | 1/18/2007 | 1/19/2007 | 1/19/2007 | A | CANC |
Troy Cobbley
|
|
|
contractor is not ready for inspection
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2007 | 1/16/2007 | 1/16/2007 | A | PASS |
Troy Cobbley
|
|
|
The remaining areas of the 2nd floor tenant inprovement are ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/10/2007 | 1/11/2007 | 1/11/2007 | A | PART |
Troy Cobbley
|
|
|
The first floor tenant area piping rough-in has passed. The piping below the stairs and into the elevator has not been installed yet. See the plans for the areason the second floor that can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 1/8/2007 | 1/9/2007 | 1/9/2007 | P | PART |
Troy Cobbley
|
|
|
The second floor wet and dry systems were the only areas inspected today. Two uprights are blocked by duct and webbing. The uprights on the dry system need to be aligned with the slope of the roof deck and then there is the insulation issue that needs to be corrected. Also the branchline over the elevator shaft has not been installed.
|