INSP-Final Inspection | 12/27/2007 | 12/27/2007 | 12/28/2007 | P | PASS |
Forrest France
|
|
|
Fire supply line permit finaled, see project related FIR permit for some activities regarding this case.
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2007 | 6/6/2007 | 6/6/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 5/10/2007 | 5/11/2007 | 5/11/2007 | A | PART |
Forrest France
|
|
|
OH rough-in is approved for cover at the hard lid ceilings on the 3rd floor elevator lobby and core restrooms.
|
INSP-Sprinkler Rough-in | 3/19/2007 | 3/19/2007 | 3/20/2007 | P | PART |
Forrest France
|
|
|
Corrections have been verified for compliance of meeting min. required depth of bury for the UG supply line piping, installation is approved for cover.
|
INSP-Sprinkler Rough-in | 3/15/2007 | 3/16/2007 | 3/16/2007 | A | FAIL |
Troy Cobbley
|
|
|
Top of underground pipe varies from 3-11 1/2 to 4-1 below the pavement. 4-6 is required. Pipe needs to be lower.
|