INSP-Final Inspection | 10/11/2007 | 10/12/2007 | 10/12/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
It appears that the only item remaining is the approval of the relocation of the fire dept connection from the west end of the building to around to the north side of the building. The forward flow test has passed.
|
INSP-Final Inspection | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per the alarm tech
|
INSP-Final Inspection | 9/17/2007 | 9/18/2007 | 9/18/2007 | A | FAIL |
Troy Cobbley
|
|
|
The inspection was for the first floor due to time constraints. There was missing ceiling tile in many locations and part of the ceiling is missing in the laundry room. Also it appears acouple of pendants are blocked by the surface mount lights in the conference room.
|
INSP-Final Inspection | 9/14/2007 | 9/17/2007 | 9/17/2007 | A | FAIL |
Troy Cobbley
|
|
|
Need the forward flush performed. I need verification that the relocation of the fire dept. connection is approved. Need caps on the fdc. Need to walk through all of the rooms to look for obstructions, light fixtures, prior to final
|
INSP-Final Inspection | 9/10/2007 | 9/13/2007 | 9/13/2007 | A | CANC |
Troy Cobbley
|
|
|
Cancel due to the fire alarm contractor not calling in his permit. Will need to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | PASS |
Troy Cobbley
|
|
|
The attic system hydro test passed.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | P | PASS |
Troy Cobbley
|
|
|
The underspaced heads have been corrected as well as the hangers in the common corridors. The sprinkler piping in the corridors can be covered. The items remaining are the attic system needs to be hydro tested due to the changes and a 24 hour test also the typical final issues such as forward flush, tags, signage.....ect.
|
INSP-Sprinkler Rough-in | 8/10/2007 | 8/13/2007 | 8/13/2007 | P | PART |
Troy Cobbley
|
|
|
The hangers on the hallway mains have been corrected accept at a couple of locations where the screws could use acouple of more turns. Approximately 60 pendant heads have been installed on 401 canopies so that the light fixtures are no longer a problem. Also I found 3 sprinkler pendants that are located less than the required 8' apart and will need to be relocated. I asked the fitter to verify no others had been missed.
|
INSP-Sprinkler Rough-in | 8/2/2007 | 8/3/2007 | 8/3/2007 | P | CANC |
Troy Cobbley
|
|
|
This is a re-inspection. Please call 1/2 hour prior to inspection. Brian F is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 7/30/2007 | 7/31/2007 | 8/1/2007 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for the items needing corrected. Mike Beerman also has a list. It includes hangers, overspaced heads and painted heads.
|
INSP-Sprinkler Rough-in | 7/17/2007 | 7/17/2007 | 7/18/2007 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the latest set of corrections. The contractor has covered piping in areas that were not approved for cover. I gave locations where piping needs to be exposed by removing the ceiling. Pipe size installed does not match plans, anti-freeze loop is all wrong, hangers....ect
|
INSP-Sprinkler Rough-in | 5/15/2007 | 5/16/2007 | 5/16/2007 | A | FAIL |
Forrest France
|
|
|
Need approved plan resubmittals prior to approval for cover at the attic dry system.
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2007 | 5/16/2007 | 5/16/2007 | A | CANC |
Forrest France
|
|
|
Pending plan resubmittals.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2007 | 5/14/2007 | 5/14/2007 | A | FAIL |
Troy Cobbley
|
|
|
The attic sprinkler system still does not match the approved plans with upright heads overspaced and too far from the deck and earthquake bracing missing. The third floor wet system hangers and tenting have been corrected. The second floor hangers have been corrected. The contractor stated that all of the plan deviations that I marked in red on the city approved plans were ok with Brian and no resubmittals required. I called Brian and he stated that was not the case. I left a correction notice with the fitter stating that resubmittals are required. I gave the fitter permission for only the second floor piping and the piping in the first floor resident rooms to be covered. All other piping is to remain uncovered until it matches the city approved plans or resubmittals are approved. The first floor and second floor hydro tests passed. The third floor hydro test failed. These floors had to be retested due to the main piping being the wrong size. I also aske the fitter for verification that the 3" sch 10 piping could be used incase the piping was submitted as plastic. The plans were not clear about this.
|
INSP-Sprinkler Rough-in | 5/10/2007 | 5/11/2007 | 5/11/2007 | A | FAIL |
Troy Cobbley
|
|
|
There are many errors including unattached hangers and inadequate tenting. Pipe sizing does not match the plans. The piping in the central first floor area does not match the plans, a loop has been installed. The anti-freeze loop shows two heads but four are actually installed and this is a remote area. Also the anti-freeze loop piping is smaller than what is shown. The revise attic piping plan was not available for inspection of the attic piping.
|
INSP-Sprinkler Rough-in | 5/10/2007 | 5/11/2007 | 5/10/2007 | A | CANC |
Troy Cobbley
|
|
|
Please call Brian prior to inspection. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 5/10/2007 | 5/10/2007 | 5/10/2007 | P | FAIL |
Troy Cobbley
|
|
|
I started the inspection on the first floor and found the first piece of pipe I looked at was the wrong size. We went to the attic system and found that what was marked on the newest drawings as as-built was not actually installed that why. This includes heads in the remote area and in the dormers. Basically no inspection was done. I spoke to Mike Beerman and he said he would get things taken care of and the inspection called back in.
|
INSP-Sprinkler Rough-in | 5/9/2007 | 5/10/2007 | 5/10/2007 | A | CANC |
Troy Cobbley
|
|
|
Contractor could not meet me when I needed to be at the project. To be rescheduled.
|