INSP-Final Inspection | 6/14/2007 | 6/14/2007 | 6/14/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 6/11/2007 | 6/12/2007 | 6/12/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed inspection.
|
INSP-Final Inspection | 6/7/2007 | 6/8/2007 | 6/8/2007 | P | PART |
Forrest France
|
|
|
Trip and alarm testing completed satisfactory, overhead install is acceptable. Items needed for final include the required 24 hr. air test per NFPA 13 and a passable UG hydrostatic test.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2007 | 6/8/2007 | 6/8/2007 | A | FAIL |
Forrest France
|
|
|
UG hydrostatic test failed due to pressure loss at the guage of 15 psi. over a two hour period.
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2007 | 6/7/2007 | 6/7/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test passed inspection, UG hydro lost 4psi. during two hour test.
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2007 | 6/7/2007 | 6/7/2007 | A | PART |
Forrest France
|
|
|
OH rough-in is acceptable.
|
INSP-Sprinkler Rough-in | 5/16/2007 | 5/16/2007 | 5/16/2007 | P | PART |
Forrest France
|
|
|
UG supply line to the point extended to the street is approved for bury.
|