INSP-Final Inspection | 10/30/2007 | 10/30/2007 | 10/30/2007 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 5/4/2007 | 5/4/2007 | 5/4/2007 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given by dave hanniman for the new areas to be occupied while the fire alarm and fire sprinkler systems are finished being installed.
|
INSP-Final Inspection | 5/4/2007 | 5/4/2007 | 5/4/2007 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Supply line flush | 4/30/2007 | 5/1/2007 | 5/1/2007 | A | PASS |
Troy Cobbley
|
|
|
underground supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 4/16/2007 | 4/17/2007 | 4/17/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 4/9/2007 | 4/9/2007 | 4/10/2007 | P | PASS |
Troy Cobbley
|
|
|
The remaining section of underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/6/2007 | 4/6/2007 | 4/6/2007 | P | NR |
Forrest France
|
|
|
UG fire supply line not yet completed for cover inspection as scheduled due to site conditions.
|
INSP-Sprinkler Rough-in | 3/22/2007 | 3/23/2007 | 3/23/2007 | A | PASS |
Troy Cobbley
|
|
|
The inbuilding riser and 10' of stubout pipe is ok to cover.
|