INSP-Final Inspection | 3/12/2008 | 3/13/2008 | 3/13/2008 | A | PASS |
Forrest France
|
|
|
Previous c/n items are complete, two painted heads replaced while on site, fire sprinkler permit finaled.
|
INSP-Final Inspection | 3/10/2008 | 3/10/2008 | 3/11/2008 | P | FAIL |
Forrest France
|
|
|
Missing some required finish items including FDC cap, "911" sign at the bell, breakaway lock at the PIV, restricted inspectors test, some items at the riser, also missing one system flow switch due to be replaced, project is not in condition for final at this time.
|
INSP-Sprinkler Rough-in | 11/26/2007 | 11/27/2007 | 11/27/2007 | A | PART |
Forrest France
|
|
|
Underground flush passed as per KR
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2007 | 11/20/2007 | 11/20/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | PART |
Forrest France
|
|
|
AG hydrostatic testing passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/21/2007 | 9/24/2007 | 9/24/2007 | P | NR |
Forrest France
|
|
|
Hydrostatic test is not ready.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | NR |
Forrest France
|
|
|
System is not pressured for hydrostatic testing.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2007 | 9/13/2007 | 9/13/2007 | P | PART |
Forrest France
|
|
|
OH rough-in is approved for cover, tenting at the second floor is okay, noted missing ball drip at the FDC check, need nailer plates at the second floor feed piping, AG hydro failed due to low start pressure, noted minor field modifications are okay.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2007 | 9/12/2007 | 9/13/2007 | A | FAIL |
Forrest France
|
|
|
Hydrostatic testing failed due to pressures below 200psi at the guage.
|