Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR07-00344
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6752 S BUSINESS WAY
Project NameFED EX
Customer Number 
ePlanReview 
Description
Scope of Work:
Bring a new 55’-0”, 6” UG service into the bldg. from an existing tapping tee. The Existing Dry pipe risers will be modified to include two new dry pipe risers (Systems 3 & 4 ) to serve the new conveyor system through out the facility. This building is fully sprinklered and shall remain so. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is not attached to any BLD #.
This fire protection work shall comply with the IFC 2003 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. 09/13/07 Revised Scope of Work As-Built:
These Approved Plans were resubmitted due to pipe size and length changes made in the field during construction which resulted in a full resubmittal of plans and supporting calculations. The noted revisions are seen as Rev #2 dated 08/23/07. Based on the calculations provided, these changes do not appear to adversely affect the operation of the remote area; in-fact the performance was improved.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/30/200710/30/200710/30/2007APASS
DetailsForrest France
Return trip for re-inspection of the two new dry systems. Corrections completed, acceptance and trip testing passed per site visit by K. Roule.
INSP-Final Inspection10/23/200710/29/200710/30/2007PFAIL
DetailsForrest France
Contractor was not ready for final inspection at the agreed time, both dry systems were off line with control valves shut, air supply lines shut, missing valve trim at both systems including drain line for the pressure switch, automatic ball drips, plugs at the 3-way air guage valves, low air switches were not set. No pre-testing or system check had been completed prior to scheduling a final acceptance test. Although the inspection failed, agreed to make a same day return trip if corrections could be made in time.
INSP-Sprinkler Rough-in/Hydro9/20/20079/21/20079/21/2007PPASS
DetailsForrest France
24 hour pneumatic testing for both dry systems passed, final pending alarm and tamper supervision, trip test, flex couplings at risers.
INSP-Sprinkler Rough-in9/20/20079/20/20079/20/2007PPART
DetailsForrest France
Begin 24 hr. air testing of the two new dry systems at 42psi each @3:30 pm.
INSP-Sprinkler Rough-in/Hydro9/18/20079/19/20079/19/2007APART
DetailsForrest France
OH hydrostatic test for the two new dry systems passed, verified resubmitted plans, rough-in is satisfactory, noted missing head guards at some locations, need to provide flexible couplings at the risers, also need to complete 24 hr. pneumatic testing for both systems.
INSP-Sprinkler Rough-in/Hydro9/17/20079/18/20079/18/2007ACANC
DetailsForrest France
Need a rough-in & overhead hydro. Please call 1/2 hour prior to inspection. Jeremy is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro8/3/20078/6/20078/6/2007AFAIL
DetailsForrest France
Field installation is not consistent with approved plans regarding main locations, pipe size, branch line routing, some head locations, etc. Per review notes, any variance affecting these components of the system will requrie plan resubmittals due to narrow calc. margins. Approved plans must match field install prior to request for field inspection, as-builts will not be accepted in this situation.