INSP-Final Inspection | 3/20/2008 | 3/21/2008 | 3/21/2008 | A | PASS |
Forrest France
|
|
|
Items on the issued correction notice verified for compliance, fire sprinkler passed final field inspection, permit finaled. NOTE: see project related FIR permit # FIR07-00365 for some field inspection notes related to this permit.
|
INSP-Final Inspection | 3/17/2008 | 3/17/2008 | 3/17/2008 | A | FAIL |
Forrest France
|
|
|
See correction notice on site for a list of defficient items including missing escutcheons, one overspaced head, painted heads, travel caps needing removal, tape and paper at some heads, etc.
|
INSP-Sprinkler Rough-in/Hydro | 2/25/2008 | 2/25/2008 | 2/25/2008 | A | PART |
Forrest France
|
|
|
Painted heads at locations previously noted have been replaced as needed.
|
INSP-Final Inspection | 1/16/2008 | 1/16/2008 | 1/16/2008 | A | PART |
Forrest France
|
|
|
Preliminary walkthrough of units only at the 2nd, 3rd and 4th floors completed today, noted painted heads at three locations and some missing escutcheons, no inspection at two units on the 3rd floor due to finishes underway, spacing appears adequate for areas inspected today, project is not ready for final at this time.
|
INSP-Sprinkler Rough-in | 11/26/2007 | 11/27/2007 | 11/27/2007 | A | PART |
Forrest France
|
|
|
Cold cavity protection at the 5th floor is satisfactory as completed to date. Noted two apts. at the SW are not finished and will need inspection prior to approval for cover, heads at the trash chute are not yet connected.
|
INSP-Sprinkler Rough-in | 11/1/2007 | 11/2/2007 | 11/2/2007 | A | PART |
Forrest France
|
|
|
Field inspection to determine adequacy of cold cavity protection and the proposal to use the exception per NFPA 13 regarding non-sprinklered combustible concealed spaces filled entirely with insulation.
|
INSP-Sprinkler Rough-in | 10/30/2007 | 10/31/2007 | 11/1/2007 | P | NR |
Forrest France
|
|
|
Rescheduled per contractor.
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic testing for the standpipe passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2007 | 10/22/2007 | 10/22/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic test for the 5th floor passed, overhead rough-in for the 5th floor completed- noted SW heads at the elevator and trash chute are not yet installed, heads at patios are not installed pending AFSA ruling, need cold cavity protection prior to ceiling cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2007 | 10/9/2007 | 10/9/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic test for the 4th floor passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2007 | 10/8/2007 | 10/8/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic re-test of the 3rd floor passed inspection, also verified DSW heads at the 4th floor patios.
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2007 | 10/5/2007 | 10/5/2007 | A | FAIL |
Forrest France
|
|
|
OH hydrostatic test for the 3rd floor failed due to pressure loss at the guage.
|
INSP-Sprinkler Rough-in/Hydro | 10/5/2007 | 10/5/2007 | 10/5/2007 | P | DEFR |
Forrest France
|
|
|
Duplicate inspection request.
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2007 | 10/4/2007 | 10/4/2007 | P | PART |
Forrest France
|
|
|
1st and 2nd floor hydrostatic tests passed, OH install is okay for cover at the 3rd floor, no cover allowed on the 4th floor until DSW heads are in place.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | FAIL |
Forrest France
|
|
|
OH hydrostatic test for the 1st floor failed due to pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 10/1/2007 | 10/1/2007 | 10/1/2007 | P | PART |
Forrest France
|
|
|
First and second floors are okay for cover as noted, one DSW at each level is not installed, one head to be added at the 1st floor, also discussed roof hose connection.
|