Permit Information
Permit NumberFIR07-00425
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 406 S 13TH ST
Project Name 
Customer Number 
ePlanReview 
Description
Original Scope of Work: Overhead Only - Phase II includes providing complete sprinkler coverage through out the Bldg. over five floors beginning from an existing 4” outlet on the basement level. A wet pipe system will be supplied from a combination Class I Standpipe sprinkler riser in Stairwell # 3. Each floor will be controlled from a local sectional control valve with exception to the fifth floor sectional control valve which will be controlled from the forth floor stair well, independent from the fifth floor. The Class I Standpipe will be located in Stairwell #4. The Basement Sprinkler system, riser and standpipe supply was installed under a separate permit. This building is fully fire sprinklered per NFPA 13 per Boise City Ordinance. All construction per the approved plans and attached comment list. This permit is attached to BLD06-00693.
09/27/07 Review Comments & Conditions of Approval:
Provide coverage on all exterior patios and balcony’s at each level per IFC 903. (Type V construction). The 5th floor patios shall be protected regardless of the roof eve overhang or lack there of. Sprinkler coverage will be verified by a Fire & Life Safety Field Inspector. As-Built plans including the additional coverage shall be resubmitted upon completion of the project or in additional plan submittal as required.
Revise the plans to include coverage in the corridor outside the bedrooms of the unit 106 located at Col. 13, 14 & D on each of the 5 floors. Sprinkler coverage will be verified by a Fire & Life Safety Field Inspector. As-Built plans including the additional coverage shall be resubmitted upon completion of the project or in additional plan submittal as required.
Revise the riser notes to include accurate Phase II details. Please include the entire square footage served from each riser and are served. As-Built plans including the required notes shall be resubmitted upon completion of the project or in additional plan submittal as required.
Provide FDC supply information where two or more bldg is being served. (Per IFC Requirements). Adequate signage will be verified by a Fire & Life Safety Field Inspector. As-Built plans including the FDC notes shall be resubmitted upon completion of the project or in additional plan submittal as required.
Sheet FP-5, a head is not located at the end of pipe in the corridor from the Kitchen in unit 503. . Sprinkler coverage will be verified by a Fire & Life Safety Field Inspector. As-Built plans including the additional coverage shall be resubmitted upon completion of the project or in additional plan submittal as required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/20/20083/21/20083/21/2008APASS
DetailsForrest France
Items on the issued correction notice verified for compliance, fire sprinkler passed final field inspection, permit finaled. NOTE: see project related FIR permit # FIR07-00365 for some field inspection notes related to this permit.
INSP-Final Inspection3/17/20083/17/20083/17/2008AFAIL
DetailsForrest France
See correction notice on site for a list of defficient items including missing escutcheons, one overspaced head, painted heads, travel caps needing removal, tape and paper at some heads, etc.
INSP-Sprinkler Rough-in/Hydro2/25/20082/25/20082/25/2008APART
DetailsForrest France
Painted heads at locations previously noted have been replaced as needed.
INSP-Final Inspection1/16/20081/16/20081/16/2008APART
DetailsForrest France
Preliminary walkthrough of units only at the 2nd, 3rd and 4th floors completed today, noted painted heads at three locations and some missing escutcheons, no inspection at two units on the 3rd floor due to finishes underway, spacing appears adequate for areas inspected today, project is not ready for final at this time.
INSP-Sprinkler Rough-in11/26/200711/27/200711/27/2007APART
DetailsForrest France
Cold cavity protection at the 5th floor is satisfactory as completed to date. Noted two apts. at the SW are not finished and will need inspection prior to approval for cover, heads at the trash chute are not yet connected.
INSP-Sprinkler Rough-in11/1/200711/2/200711/2/2007APART
DetailsForrest France
Field inspection to determine adequacy of cold cavity protection and the proposal to use the exception per NFPA 13 regarding non-sprinklered combustible concealed spaces filled entirely with insulation.
INSP-Sprinkler Rough-in10/30/200710/31/200711/1/2007PNR
DetailsForrest France
Rescheduled per contractor.
INSP-Sprinkler Rough-in/Hydro10/22/200710/23/200710/23/2007APART
DetailsForrest France
Hydrostatic testing for the standpipe passed.
INSP-Sprinkler Rough-in/Hydro10/19/200710/22/200710/22/2007APART
DetailsForrest France
OH hydrostatic test for the 5th floor passed, overhead rough-in for the 5th floor completed- noted SW heads at the elevator and trash chute are not yet installed, heads at patios are not installed pending AFSA ruling, need cold cavity protection prior to ceiling cover.
INSP-Sprinkler Rough-in/Hydro10/8/200710/9/200710/9/2007APART
DetailsForrest France
OH hydrostatic test for the 4th floor passed.
INSP-Sprinkler Rough-in/Hydro10/8/200710/8/200710/8/2007PPART
DetailsForrest France
OH hydrostatic re-test of the 3rd floor passed inspection, also verified DSW heads at the 4th floor patios.
INSP-Sprinkler Rough-in/Hydro10/4/200710/5/200710/5/2007AFAIL
DetailsForrest France
OH hydrostatic test for the 3rd floor failed due to pressure loss at the guage.
INSP-Sprinkler Rough-in/Hydro10/5/200710/5/200710/5/2007PDEFR
DetailsForrest France
Duplicate inspection request.
INSP-Sprinkler Rough-in/Hydro10/4/200710/4/200710/4/2007PPART
DetailsForrest France
1st and 2nd floor hydrostatic tests passed, OH install is okay for cover at the 3rd floor, no cover allowed on the 4th floor until DSW heads are in place.
INSP-Sprinkler Rough-in/Hydro10/3/200710/3/200710/3/2007PFAIL
DetailsForrest France
OH hydrostatic test for the 1st floor failed due to pressure loss at the guage.
INSP-Sprinkler Rough-in10/1/200710/1/200710/1/2007PPART
DetailsForrest France
First and second floors are okay for cover as noted, one DSW at each level is not installed, one head to be added at the 1st floor, also discussed roof hose connection.