INSP-Final Inspection | 10/22/2007 | 10/22/2007 | 10/22/2007 | P | PASS |
Forrest France
|
|
|
Corrections verified for completion, inspection passed, permit finaled.
|
INSP-Final Inspection | 10/18/2007 | 10/19/2007 | 10/19/2007 | A | FAIL |
Forrest France
|
|
|
Overspaced coverage due to missing upright heads at two locations in the SW corner of the tenant space, see plans for annotations, previously noted items are finished. Contractor is advised to complete a thorough field review of the installation prior to scheduling final inspection.
|
INSP-Final Inspection | 10/17/2007 | 10/18/2007 | 10/18/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked. This will need to be rescheduled.
|
INSP-Final Inspection | 10/15/2007 | 10/16/2007 | 10/16/2007 | A | FAIL |
Forrest France
|
|
|
See approved plans for areas defficient including overspaced heads, blocked heads, missing coverage, one pendent below max. listed distance from the deck.
|
INSP-Sprinkler Rough-in | 10/11/2007 | 10/12/2007 | 10/12/2007 | P | PART |
Forrest France
|
|
|
OH rough-in is approved as noted on stamped plan set.
|
INSP-Sprinkler Rough-in | 10/3/2007 | 10/3/2007 | 10/3/2007 | P | PART |
Forrest France
|
|
|
Added head at the storage closet below the stairs at the main entrance is acceptable, noted cloud ceilings obstructing coverage and one deleted hard lid ceilng.
|
INSP-Sprinkler Rough-in | 9/13/2007 | 9/13/2007 | 9/13/2007 | P | PASS |
Troy Cobbley
|
|
|
The mechanical chase in room 143 has been provided a sprinkler head and is ok to cover. The mechanical chase in room 150 is non-combustible and is ok to cover. These are the only two areas inspected.
|
INSP-Sprinkler Rough-in | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | CANC |
Troy Cobbley
|
|
|
Due to the abundance of inspections today there was not adequate time to perform this one. It will need to be rescheduled.
|