INSP-Final Inspection | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Supply line flush | 7/6/2007 | 7/6/2007 | 7/6/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 7/5/2007 | 7/5/2007 | 7/5/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Sprinkler Rough-in | 6/22/2007 | 6/22/2007 | 6/26/2007 | P | CANC |
Troy Cobbley
|
|
|
This is a duplicate inspection.
|
INSP-Sprinkler Rough-in | 6/22/2007 | 6/25/2007 | 6/25/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line is approved for cover, noted lacking method for seismic clearance where ductile riser will pass through the floor slab, also missing flange and cap at the top of the riser.
|