INSP-Final Inspection | 4/9/2008 | 4/11/2008 | 4/11/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 3/20/2008 | 3/21/2008 | 3/21/2008 | A | FAIL |
Troy Cobbley
|
|
|
Just need to verify the fire proofing has been repaired to final. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2008 | 3/20/2008 | 3/20/2008 | A | PASS |
Troy Cobbley
|
|
|
Hydro test passed. Need certification on the new backflow and inspection tag on the anti-freeze system riser. The fire proofing has not been repiared yet.
|
INSP-Sprinkler Rough-in | 3/11/2008 | 3/12/2008 | 3/12/2008 | A | PASS |
Troy Cobbley
|
|
|
Need the fire proofing repaired in the storage area and the 401 canopies(heads lowered) installed as per discussion. The galvanized piping/fittings on the roof are ok as per discussion with Brian Johnson.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2008 | 2/21/2008 | 2/21/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping that passed rough-in inspection today.
|
INSP-Sprinkler Rough-in | 2/19/2008 | 2/20/2008 | 2/20/2008 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow morning
|
INSP-Sprinkler Rough-in | 1/31/2008 | 2/5/2008 | 2/5/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations approved for cover.
|
INSP-Sprinkler Rough-in | 1/23/2008 | 1/24/2008 | 1/24/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the room locations where the piping is ok to cover.
|
INSP-Sprinkler Rough-in | 1/10/2008 | 1/11/2008 | 1/11/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations that are ok to cover.
|
INSP-Sprinkler Rough-in | 1/2/2008 | 1/3/2008 | 1/3/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations of piping inspected today.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2007 | 12/19/2007 | 12/19/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for additional rooms where the piping is ok to cover.
|
INSP-Sprinkler Rough-in | 12/11/2007 | 12/12/2007 | 12/12/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the two additional rooms where the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in | 12/4/2007 | 12/6/2007 | 12/6/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered. Todays inspection was for three jail cells.
|
INSP-Sprinkler Rough-in | 11/7/2007 | 11/8/2007 | 11/8/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations that are approved for cover. They will have todays date.
|
INSP-Sprinkler Rough-in | 11/1/2007 | 11/1/2007 | 11/2/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the piping locations inspected for today and ok to cover.
|
INSP-Sprinkler Rough-in | 9/14/2007 | 9/18/2007 | 9/18/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for piping locations where the piping can be covered.
|