INSP-Final Inspection | 1/17/2008 | 1/18/2008 | 1/18/2008 | A | PASS |
Forrest France
|
|
|
Final passed, flow switch cover attatched while on site, tape and paper at one garage sw to be removed when painting is finished, CPVC at the riser to meet mfg. installation guidelines.
|
INSP-Final Inspection | 1/16/2008 | 1/17/2008 | 1/17/2008 | P | NR |
Forrest France
|
|
|
Project is not ready for final at this time per contractor, inspection to be rescheduled as discussed.
|
INSP-Supply line flush | 12/12/2007 | 12/12/2007 | 12/12/2007 | P | PART |
Forrest France
|
|
|
Under ground flush OK. KR
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | PART |
Forrest France
|
|
|
Corrections have been completed, tenting is acceptable, OH fire sprinklers are okay for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2007 | 8/15/2007 | 8/15/2007 | P | FAIL |
Forrest France
|
|
|
Two heads on the second floor are obstructed by ceilng mounted beams, noted three areas lacking sufficient cold cavity protection, one SW head adjusted while on site.
|
INSP-Sprinkler Rough-in | 8/13/2007 | 8/14/2007 | 8/14/2007 | P | NR |
Forrest France
|
|
|
OH rough-in not yet ready for complete cover inspection as requested.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2007 | 8/13/2007 | 8/13/2007 | P | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 8/11/2007 at 11:52:57 AM. Contact: ###-####.
|