Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR07-00606
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3101 W CASSIA ST
Project NameSOUTH JUNIOR HIGH SCHOOL
Customer Number 
ePlanReview 
Description
12/26/07 Plan Review: Overhead
These plans were resubmitted to as requested based on then plan review comments dated 11/20/07.
11/20/07 Revised Scope of Work: Overhead
These plans were resubmitted to as requested based on then plan review comments dated 07/30/07. The resubmittal also included plan modifications of which appear to have been the result of construction coordination with the architect and or the other trades involved in this project. The modifications included the relocation of several feed and cross mains which resulted in the submittal of new calculations to support the modifications. The heads in the Athletic Gear Locker have been omitted.
Scope of Work: Overhead Only
The overhead work consist of adding sprinkler coverage through out, beginning from the first flange above finished floor in the riser room on the South side of the140,121-ft/2 two story structure. The sprinkler coverage will be served from four wet risers. Each floor supply will be controlled separately.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-00007. This permit is also attached to the Underground work permit FIR07-00505.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/15/20094/15/20094/15/2009PPASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection10/13/200810/13/200810/13/2008PNR
DetailsForrest France
Missing ceiling tile at three vestibules, missing escutcheons at two locations.
INSP-Final Inspection10/8/200810/9/200810/9/2008PPART
DetailsForrest France
Escutcheons at the auditorium and classroom A106 have been installed, missing one canopy at the south side vestibule.
INSP-Sprinkler Rough-in8/14/20088/15/20088/15/2008APART
DetailsForrest France
Heads at the drop ceiling classroom A106 are good for cover, recieved as-built plans for documentation of field changes.
INSP-Sprinkler Rough-in/Hydro8/11/20088/11/20088/11/2008APART
DetailsForrest France
Final pending completion of work in area A including classroom A106, prop storage, and the auditorium, also need to provide resubmittals for field changes in pipe routing and added upright and pendent heads in the auditorium.
INSP-Sprinkler Rough-in8/5/20088/6/20088/6/2008APART
DetailsForrest France
Additional pendent heads at the west side of the auditorium in the angled hard lid soffit are okay for cover pending plans are provided reflecting field installation.
INSP-Sprinkler Rough-in/Hydro8/4/20088/4/20088/4/2008PPART
DetailsForrest France
Completed forward flow testing, noted some items repaired including proper head temps at skylights in the library, added head at the riser room, storage room area separation has been installed, spacing adjusted where needed, tampers and flow switches tested. Still need as-built plans as requested, area A correction items are not finished.
INSP-Sprinkler Rough-in7/31/20088/1/20088/1/2008PFAIL
DetailsForrest France
Noted locations on plan set at areas G and H in need of correction including overspaced heads at the weight room and stair B09, provide correct temp. heads at the three skylights, noted some heads still covered by foil due to painting in progress-some items repaired while on site. Still need area separation at the storage room C28, provide as-builts for changes at the electrical and mech. rooms, noted one blocked head at the riser room, no provision for forward flow testing at the riser has been provided. Area A deficiencies include prop storage calcs, as-builts for added upright protection, high temp head at the unit heater in the storage room, classroom A06 is not finished, angled soffit at the west side of the auditorium is obstructed.
INSP-Sprinkler Rough-in7/30/20087/31/20087/31/2008PPART
DetailsForrest France
Correction notice items regarding areas B and D plan sheet FP5 are finished, discussed balance of project to be inspected, some areas not yet ready per contractor-repairs incomplete.
INSP-Sprinkler Rough-in7/30/20087/30/20087/30/2008PFAIL
DetailsForrest France
Third reinspection for areas B and D plan sheet FP5 failed due to items including overspaced head at corridor A11, overspaced pendent at the girls locker room B40, missing branch line below the stairs at storage room B13 including three SSU heads, need intermediate temp. head adjacent to the supply register at girls room B38-noted per inspection completed 7/10, missing sprinkler coverage at the accessible mechanical room between mens B44 and womens B43 restrooms, notified general contractor to provide area separation between sprinklered and non-sprinklered areas at the storage room C228, one painted head replaced while on site. Ten item correction notice from yesterdays inspection is finished.
INSP-Sprinkler Rough-in7/29/20087/30/20087/30/2008ACANC
DetailsForrest France
Jerry is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in7/28/20087/29/20087/29/2008AFAIL
DetailsForrest France
Reinspection for areas B and D per plan sheet FP5 failed due to several deficient or missing items including overspaced upright at a utility room, missing seismic clearance or flex couplings at the 4" main NW corner of corridor D35, overspaced hanger at the vendors room, overspaced pendent off an adjacent wall corridor B01, painted head at the cafeteria soffit, painted heads at storage room C29, heads at the kitchen are still overspaced as noted per inspection completed 7/10, pendent head overspaced in corridor B06, head at the elevator equipment room is overspaced, exposed wood at the elevator lobby per note from inspection completed 7/10 is not yet protected or removed, concluded inspection at this time due to the excessive number of corrections. Also completed third final reinspection of areas J, I, E, and F classroom wings 1st and 2nd floors-NOTE: these areas passed. Per contractor, area A corrections are not finished at this time.
INSP-Sprinkler Rough-in7/25/20087/28/20087/28/2008AFAIL
DetailsForrest France
Second reinspection for areas E, F, J and I, failed due to missed or incorrect repairs including exceeded min. spacing for heads at two locations, pendent head at a storage closet still does not meet obstruction table per NFPA 13 8.6.5.1.2, mixed heads at second floor classroom 103. Some items verified for correction initialed okay on plans with today's date.
INSP-Sprinkler Rough-in7/23/20087/24/20087/24/2008AFAIL
DetailsForrest France
OH re-inspection for area A failed due to several deficient items including overspaced upright coverage at the auditorium, SW heads at an electrical room are too low, foil at heads in the stage area, piping changes for branch line feeds in the hyd. calc area at the prop storage room, missing flex couplings at two locations, lacking coverage at the administration vestibule, missing EQ brace at the admin. main, new plans need to reflect the added uprights and piping changes for mains and branchlines. Some issues previously noted are corrected including seismic bracing at the auditorium and added coverage for the stair landing and main entry vestibule.
INSP-Sprinkler Rough-in7/21/20087/22/20087/22/2008PFAIL
DetailsForrest France
Reinspection completed for Areas E,F,I and J failed due to several deficient items including 3 missing hangers, 4 missing upright heads at two mechanical rooms, overspaced pendent heads at two locations in the common corridor, overspaced heads at one classroom, missing all seismic bracing at the upper mechanical room, overspaced classroom vestibule x2, min. spacing is exceeded at a science room, light fixture obstruction at a storage room, one overspaced head off an adjacent wall in classroom J10, need to verify correct temp. heads at the room marked "kiln room". Concluded inspection until repairs are made and project is ready for field review.
INSP-Sprinkler Rough-in7/16/20087/16/20087/16/2008PFAIL
DetailsForrest France
Re-inspection for noted defficiencies failed due to non-completion of several items, noted missing coverage at the NE entry vestibule, incorrect head spacing, non-compliant seismic bracing, several field modifications in pipe routing compared to the approved plan set, lacking hangers, etc. Contractor to perform a complete walkthrough of the project regarding necessary adjustments and corrections for code compliance prior to the next scheduled site visit as discussed.
INSP-Sprinkler Rough-in/Hydro7/15/20087/16/20087/16/2008PPART
DetailsForrest France
OH hydrostatic test for the admin system passed.
INSP-Sprinkler Rough-in/Hydro7/14/20087/15/20087/15/2008PDEFR
DetailsForrest France
Rescheduled per contractor request.
INSP-Sprinkler Rough-in7/11/20087/14/20087/14/2008ACANC
DetailsTroy Cobbley
Cancelled due to time constraints. I left a message on pat's voice mail.
INSP-Sprinkler Rough-in7/11/20087/11/20087/11/2008PPART
DetailsTroy Cobbley
See the city approved plans for locations where ceilings can be installed and where additional deficiencies have been found such as improperly installed retaining straps, overspaced heads, missing heads, painted heads and heads blocked by the shower pedastals.
INSP-Sprinkler Rough-in/Hydro7/10/20087/10/20087/10/2008PPART
DetailsTroy Cobbley
See the city approved resubmittals for the areas that are ok to cover. They include the cafeteria and the corridor to the immediate north. The surrounding hallways did not have the earthquaking installed on the 2 1/2" mains.
INSP-Sprinkler Rough-in6/5/20086/6/20086/6/2008AFAIL
DetailsForrest France
Overhead rough-in inspection for the auditoruim area failed due to overspaced upright heads, missing coverage at the SW stair landing, provide flexible couplings at the 4' main where lacking correct seismic clearance at the block walls east and west sides, noted changes in pipe routing of the 4" main not indicated on plans at the intersection of the catwalk and cross main, the north half of the pendent heads at cloud ceilings are not yet complete, noted site made EQ braces consisting of unistrut and bent 3/8" all-thread rod attatched to truss webs are not approved or listed for this use-provide materials and components installed in such a way to meet appropriate guidelines per NFPA 13.
INSP-Sprinkler Rough-in/Hydro5/29/20085/30/20085/30/2008APART
DetailsForrest France
OH hydrostatic test for the auditorium system passed.
INSP-Sprinkler Rough-in/Hydro5/29/20085/30/20085/30/2008PCANC
DetailsForrest France
Duplicate inspection request.
INSP-Sprinkler Rough-in/Hydro5/28/20085/29/20085/29/2008APART
DetailsForrest France
See previous inspection notes for activities to date.
INSP-Sprinkler Rough-in/Hydro5/22/20085/23/20085/23/2008APART
DetailsForrest France
OH hydrostatic testing for system #4 completed without pressure loss.
INSP-Sprinkler Rough-in5/21/20085/22/20085/22/2008AFAIL
DetailsForrest France
Re-inspection completed for overhead rough-in at the second floor area I, noted several items still not corrected including seismic clearance at mains and block walls, missing or overspaced hangers, poorly attatched retaining straps, stairways are not finished, pendent heads at two locations in the corridor are overspaced off adjacent classroom entry vestibules. NOTE: Agreed to allow ceiling cover at the classrooms only due to contractor repairing missing hangers and ret. straps during the field inspection. See stamped plan set for annotated defficiencies.
INSP-Sprinkler Rough-in/Hydro5/19/20085/20/20085/20/2008PPART
DetailsForrest France
Area J second floor classrooms only okayed for cover-four missing retaining straps attatched by an apprentice while on site, still need access above hard lids at the restrooms for inspection, upright heads at the RR mechanical chase need adjustment.
INSP-Sprinkler Rough-in5/12/20085/12/20085/12/2008PFAIL
DetailsForrest France
OH rough-in inspection completed for areas G and H, see re-lined annotations on plan set for marked defficiencies including bracing, hangers, seismic clearance, spacing, obstructions at various locations, noted added head at the top of the SE elevator hoistway does not appear required and is not indicated on plans, tops of stairways and three skylights in the library are not yet installed, four head guards are missing at the gym.
INSP-Sprinkler Rough-in/Hydro5/9/20085/12/20085/12/2008APART
DetailsForrest France
OH hydrostatic testing for system #3 only (gym system) passed.
INSP-Sprinkler Rough-in5/8/20085/9/20085/9/2008APART
DetailsForrest France
Verification for beam clamp retaining strap attatchments at the first floor NW and SW classroom wings only, noted overspaced hangers at three locations SW wing.
INSP-Sprinkler Rough-in5/2/20085/5/20085/8/2008AFAIL
DetailsForrest France
Rough-in inspection for the second floor areas J and I failed due to several items including incorrect seismic bracing, lacking clearance at mains and block wall penetrations, overspaced hangers, beam clamp retatining straps not attatched, pipe routing has been changed from approved plans at some locations including mains and branch lines as red lined on plans, hard lid ceilings at the restrooms have been installed without a cover inspection-need to provide access, stairways and electrical rooms are not yet completed, piping at the storage areas under the stair landings 1st floor does not match plan and SW heads installed are too low, several added branch line hangers at the first floor classroom wings are missing retaining strap attatchment.
INSP-Sprinkler Rough-in/Hydro5/1/20085/2/20085/5/2008PPART
DetailsForrest France
OH hydrostatic test passed for system #2 only.
INSP-Sprinkler Rough-in3/24/20083/24/20083/24/2008PNR
DetailsForrest France
INSP-Sprinkler Rough-in3/10/20083/11/20083/11/2008PPART
DetailsForrest France
Field inspection completed for the 2nd floor media center area seismic attatchments for beam clamps at hanger rods.
INSP-Sprinkler Rough-in3/3/20083/4/20083/5/2008PFAIL
DetailsForrest France
See areas marked on approved plans for correction items including areas E and F first floor.
INSP-Sprinkler Rough-in/Hydro3/5/20083/5/20083/5/2008AFAIL
DetailsForrest France
Overhead rough-in inspection completed for the first floor areas E and F, noted some defficient items including missing EQ bracing, need to provide correct seismic clearance at two locations where 4" main meets block walls, remove the ball valve in the piping to the elevator pit sprinkler, the electrical rooms and storage areas under stairways are not yet complete, some hangers will need replaced due to damage, missing retaining straps installed while on site, noted possible overspacing at heads in the corridors due to adjacent vestibules, head at the trophy case wall recess may not be required.
INSP-Sprinkler Rough-in2/14/20082/15/20082/15/2008PPART
DetailsForrest France
Inspection for retaining straps at beam clamp hangers prior to cover at the band, choir and practice rooms including the adjacent restrooms.
INSP-Sprinkler Rough-in1/8/20081/9/20081/9/2008APART
DetailsForrest France
Verified seismic restraint attatchments for beam clamps installed at the locker room areas on the east side of the building prior to fireproofing.
INSP-Conference12/17/200712/17/200712/17/2007PDONE
DetailsForrest France
Inspection to verify seismic restraints for beam clamp hanger attatchments for the cafeteria area prior to fireproofing.