INSP-Final Inspection | 8/21/2007 | 8/21/2007 | 8/21/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit for the TI modifications passed.
|
INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | PART |
Forrest France
|
|
|
Final pending installation of ceiling tile and escutcheons at all areas.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | PART |
Forrest France
|
|
|
Verified required corrections have been made, overhead installation is approved for cover at the drop ceilings.
|
INSP-Final Inspection | 8/16/2007 | 8/16/2007 | 8/16/2007 | P | CANC |
Troy Cobbley
|
|
|
The sprinkler fitter needs additional time to complete the work. He is going to reschedule for tomorrow. No inspection performed.
|
INSP-Sprinkler Rough-in | 8/16/2007 | 8/16/2007 | 8/16/2007 | P | CANC |
Troy Cobbley
|
|
|
The sprinkler fitter needs additional time to complete the work. He is going to reschedule for tomorrow. No inspection performed.
|
INSP-Final Inspection | 8/14/2007 | 8/15/2007 | 8/15/2007 | A | FAIL |
Forrest France
|
|
|
Two heads at the waiting area exceed min. spacing allowed, need to provide verification that the existing system design will support more than one head piped off a single 1" outlet (noted 4 heads are supplied off one 1" outlet at the lobby) or install heads as shown on approved plan.
|