INSP-Final Inspection | 1/25/2008 | 1/28/2008 | 1/28/2008 | A | PASS |
Forrest France
|
|
|
Fire alarm system modifications verified for compliance, permit finaled.
|
INSP-Conference | 1/22/2008 | 1/22/2008 | 1/22/2008 | P | DONE |
Forrest France
|
|
|
For project inspection schedules, date set as discussed.
|
INSP-Final Inspection | 12/5/2007 | 12/6/2007 | 12/6/2007 | A | FAIL |
Forrest France
|
|
|
Need to provide fire alarm notification at two conference rooms (these rooms are indicated on plans as "office"), provide cover plates at two locations where pull stations have been moved, adjust the fire door at the elevator for complete closure, will verify new nac at next inspection, the south corridor manaul pull and the remainder of devices tested okay.
|
INSP-Conference | 12/4/2007 | 12/4/2007 | 12/4/2007 | A | DONE |
Forrest France
|
|
|
Project site inspection schedule.
|