Permit Information
Permit NumberFIR07-00726
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 8534 W ELISA ST
Project NameVictory Business Park BLD B
Customer Number 
ePlanReview 
Description
overheadScope of Work: Overhead & Underground
The Underground scope of work includes connecting to an existing 6” C-900 capped line located 15’-0” out from the bldg. which was provided by others. Run the new section of 6” C-900 out and up into the riser room. The Underground supply will be controlled from a Wall PI located on the South side of the Bldg. The overhead fire sprinkler scope of work includes installing a 6” wet riser and a compound grid system to serve through out the entire 17,925-ft/2 bldg. The new warehouse will be built for future racking system as indicated on these plans sheet FP-2. Any future racking plans shall be submitted under a separate permit. A 1.5” hose system will also be installed designed to reach all portions of the bldg. in accordance with NFPA13 chapter 12. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-02012 & UG permit FIR07-00248.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/7/20081/9/20081/9/2008APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in12/10/200712/11/200712/11/2007APASS
DetailsTroy Cobbley
Sprinkler roughin passed. Piping can be covered in the layin ceiling areas. Could not perform the forward flush due to a guage problem.
INSP-Sprinkler Rough-in/Hydro11/1/200711/2/200711/2/2007PPASS
DetailsTroy Cobbley
Overhead hydro test passed.
INSP-Sprinkler Rough-in/Hydro10/26/200710/26/200710/26/2007PFAIL
DetailsTroy Cobbley
OH hydro test failed
INSP-Sprinkler Rough-in/Hydro10/24/200710/25/200710/25/2007PFAIL
DetailsTroy Cobbley
Inspection was scheduled for afternoon but due to Micron I tried to do it this morning. I found the guage below 200 psi and the fdc and the riser/header not part of the test.
INSP-Sprinkler Rough-in10/22/200710/23/200710/23/2007APART
DetailsTroy Cobbley
The lower level sprinkler piping is ok to cover. Corrections still need to be made to the upper level sprinkler coverage.
INSP-Sprinkler Rough-in10/22/200710/22/200710/22/2007PFAIL
DetailsTroy Cobbley
See the city approved plans for the locations of the deficiencies. The sprinkler piping is not ok to cover.