INSP-Final Inspection | 1/7/2008 | 1/9/2008 | 1/9/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 12/10/2007 | 12/11/2007 | 12/11/2007 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler roughin passed. Piping can be covered in the layin ceiling areas. Could not perform the forward flush due to a guage problem.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2007 | 11/2/2007 | 11/2/2007 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/26/2007 | 10/26/2007 | 10/26/2007 | P | FAIL |
Troy Cobbley
|
|
|
OH hydro test failed
|
INSP-Sprinkler Rough-in/Hydro | 10/24/2007 | 10/25/2007 | 10/25/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was scheduled for afternoon but due to Micron I tried to do it this morning. I found the guage below 200 psi and the fdc and the riser/header not part of the test.
|
INSP-Sprinkler Rough-in | 10/22/2007 | 10/23/2007 | 10/23/2007 | A | PART |
Troy Cobbley
|
|
|
The lower level sprinkler piping is ok to cover. Corrections still need to be made to the upper level sprinkler coverage.
|
INSP-Sprinkler Rough-in | 10/22/2007 | 10/22/2007 | 10/22/2007 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for the locations of the deficiencies. The sprinkler piping is not ok to cover.
|