Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR07-00735
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10751 W OVERLAND RD
Project NameFRED MEYER
Customer Number 
ePlanReview 
Description
overhead - Phase 3 (service deli & garden ctr.)Scope of Work:
Modify the existing dry system by extending a 4” main out into the Garden are to supply 30 new up-right heads. (FP-4 Dated 08/07) Additional work will be done in the Meat/Seafood area where heads will be relocated and added to accommodate a new wall and ceiling layout. (FP-3 Dated 08/2007) In the produce area, 4 pendant heads will be removed as the ceiling will be permanently removed. (FP-3 Dated 08/2007) The existing air compressor will be replaced with a new 12.8cfm compressor. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-00948. This permit is also attached to FIR07-00642.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/1/200711/1/200711/1/2007PPASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in10/30/200710/31/200710/31/2007AFAIL
DetailsTroy Cobbley
401canopies need to be installed in the restrooms where lights are blocking pendant heads. One head needs to be added at a fixture on the sales floor and two heads are located too close to one another at another fixture on the sales floor. Plans need to be resubmitted to the city of boise due to the amount of added heads caused by the fixtures. The scope of work calls for the air compressor to be changed out which has not been done yet.
INSP-Sprinkler Rough-in/Hydro9/27/20079/28/20079/28/2007PPASS
DetailsTroy Cobbley
24 hour air test passed
INSP-Sprinkler Rough-in9/26/20079/27/20079/27/2007PPART
DetailsTroy Cobbley
The 24 hour air test for the Garden Center was started at 11:00 with 55 psi on the guage.
INSP-Sprinkler Rough-in/Hydro9/24/20079/24/20079/24/2007PPASS
DetailsTroy Cobbley
Hydro test of the garden dry pipe system passed.
INSP-Sprinkler Rough-in9/18/20079/19/20079/19/2007APART
DetailsTroy Cobbley
The overhead piping in the garden area only is ok. The tie with the store system has not been made yet. The four way bracing at the 4" drop down is not done yet. It appears that the hydraulic node points in the calculations are not connected correctly. I contacted Brian about this.