INSP-Final Inspection | 8/19/2008 | 8/20/2008 | 8/20/2008 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/18/2008 | 8/19/2008 | 8/19/2008 | A | PART |
Forrest France
|
|
|
Riser tamper and alarm supervision tested okay, forward flow completed, need to request project related UG permit for final, final walkthrough not completed at this time.
|
INSP-Final Inspection | 8/18/2008 | 8/18/2008 | 8/18/2008 | P | NR |
Forrest France
|
|
|
Project is not ready for final inspection, outside waterflow bell must also be functional.
|
INSP-Sprinkler Rough-in | 6/23/2008 | 6/23/2008 | 6/23/2008 | P | PART |
Forrest France
|
|
|
Inspection for overhead antifreeze and wet systems at the second floor level completed acceptable, as-built plans for field changes at the antifreeze system okayed, see dated initials on plans. NOTE: cover approval pending inspection for tenting when finished.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2008 | 5/6/2008 | 5/6/2008 | A | PART |
Troy Cobbley
|
|
|
First floor wet system and second floor anti-freeze system hydro tests passed. First floor sprinkler piping rough-in is passed and the piping can be covered. See the city approved plans for the location of one pendant that needs relocated and one pendant that needs to be added on the first floor. The second floor anti-freeze piping does not quite match the plans. Mike is going to have a set of as-builts made with modified hydraulic calculations for the next inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2008 | 5/5/2008 | 5/5/2008 | A | CANC |
Forrest France
|
|
|
Overbooked
|
FIR-Aging Inspection | 2/1/2008 | 2/1/2008 | 2/1/2008 | | PART |
Forrest France
|
|
|
Site work in progress, installation is not ready for inspection at this time.
|