Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR07-00863
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 1880 W JUDITH LN
Project Name 
Customer Number 
ePlanReview 
Description
Scope of Work: Overhead - Under a separate permit, the Underground scope of work included connecting to an existing 6” C-900 capped line located 26’-0” out from the bldg, which was provided by others. (United Water) Run the new 26’-0” section of 6” C-900 out and up into the 1 hour rated riser room. The overhead fire sprinkler scope of work includes installing a 4” reduced pressure back flow device & wet riser. A wet grid system will serve through out the first and second floors. An antifreeze system will serve the cold attic space. (Roof) The roof system will also be a grid type system. The second floor will be open ceiling to the roof deck and will be protected from the roof system at the roof until tenant build out. The second floor system will consist of piping only during this phase. The second floor piping will be drained and dry until tenet build out. The first and second floors supplies will be controlled separately. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-02248 & UG permit FIR07-00835.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/19/20088/20/20088/20/2008APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection8/18/20088/19/20088/19/2008APART
DetailsForrest France
Riser tamper and alarm supervision tested okay, forward flow completed, need to request project related UG permit for final, final walkthrough not completed at this time.
INSP-Final Inspection8/18/20088/18/20088/18/2008PNR
DetailsForrest France
Project is not ready for final inspection, outside waterflow bell must also be functional.
INSP-Sprinkler Rough-in6/23/20086/23/20086/23/2008PPART
DetailsForrest France
Inspection for overhead antifreeze and wet systems at the second floor level completed acceptable, as-built plans for field changes at the antifreeze system okayed, see dated initials on plans. NOTE: cover approval pending inspection for tenting when finished.
INSP-Sprinkler Rough-in/Hydro5/5/20085/6/20085/6/2008APART
DetailsTroy Cobbley
First floor wet system and second floor anti-freeze system hydro tests passed. First floor sprinkler piping rough-in is passed and the piping can be covered. See the city approved plans for the location of one pendant that needs relocated and one pendant that needs to be added on the first floor. The second floor anti-freeze piping does not quite match the plans. Mike is going to have a set of as-builts made with modified hydraulic calculations for the next inspection.
INSP-Sprinkler Rough-in/Hydro5/2/20085/5/20085/5/2008ACANC
DetailsForrest France
Overbooked
FIR-Aging Inspection2/1/20082/1/20082/1/2008 PART
DetailsForrest France
Site work in progress, installation is not ready for inspection at this time.