INSP-Final Inspection | 6/3/2008 | 6/4/2008 | 6/4/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 5/12/2008 | 5/13/2008 | 5/13/2008 | P | PART |
Troy Cobbley
|
|
|
24 hr air test started at 10:30 with 43psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2008 | 2/15/2008 | 2/15/2008 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection number called in.
|
INSP-Sprinkler Rough-in | 2/12/2008 | 2/13/2008 | 2/13/2008 | A | FAIL |
Troy Cobbley
|
|
|
The inspection today was for the insulation in the overbuilds. When the bottom layer of insulation was removed I found that the overbuild had not been filled with insulation. The job superintendant stated that he would get them entirely filled and call in another inspection for tomorrow.
|
INSP-Supply line flush | 1/8/2008 | 1/8/2008 | 1/8/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/19/2007 | 12/19/2007 | 12/20/2007 | P | PASS |
Troy Cobbley
|
|
|
Under ground hydro passed.KR
|
INSP-Sprinkler Rough-in/Hydro | 11/15/2007 | 11/15/2007 | 11/16/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground for the west building is ok to cover. I notified the general contractor and the fire sprinkler contractor that as with the east building, conduit should be installed prior to pavement so that the PIV tamper switch can be monitored.
|
INSP-Sprinkler Rough-in | 11/14/2007 | 11/14/2007 | 11/15/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping for the east building is ok for cover.
|