INSP-Final Inspection | 12/9/2008 | 12/10/2008 | 12/10/2008 | A | PASS |
Forrest France
|
|
|
Correction items repaired, final inspection passed, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/31/2008 | 11/6/2008 | 11/6/2008 | A | PART |
Forrest France
|
|
|
Fire sprinkler modifications per the scope of work indicated are acceptable per stamped plans, final pending seismic bracing completion at the reconfigured riser.
|
INSP-Final Inspection | 10/31/2008 | 11/4/2008 | 10/31/2008 | A | CANC |
Forrest France
|
|
|
Phone #: ###-#### Internet Inspection Request from: Wayne Berry Inspection cancelled from web by: Wayne Berry
|
INSP-Conference | 10/14/2008 | 10/15/2008 | 10/16/2008 | A | DONE |
Forrest France
|
|
|
On site conference regarding fire sprinkler work at service isle 2421.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/10/2008 | 9/11/2008 | P | PART |
Forrest France
|
|
|
Hydrostatic testing for the new 6" main completed.
|
INSP-Sprinkler Rough-in | 8/19/2008 | 8/20/2008 | 8/20/2008 | A | PART |
Forrest France
|
|
|
The new 6" main above the sheetrock ceiling at the womens restroom is okay for cover, noted one lateral sway brace to be correctly attatched at the beam per discussion.
|
FIR-Aging Inspection | 5/13/2008 | 5/13/2008 | 5/12/2008 | | NR |
Forrest France
|
|
|
Pending site inspection request
|