INSP-Final Inspection | 1/15/2008 | 1/16/2008 | 1/16/2008 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 12/31/2007 | 1/2/2008 | 1/2/2008 | A | FAIL |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover. Project can not be finaled as requested due to missing ceiling tile.
|
INSP-Final Inspection | 12/27/2007 | 12/28/2007 | 12/28/2007 | A | NR |
Troy Cobbley
|
|
|
Called Brian with Treasure Valley twice and left two messages, went to the site twice and found that the doors were locked.Could not perform any inspection. KR
|
INSP-Sprinkler Rough-in/Hydro | 12/26/2007 | 12/27/2007 | 12/27/2007 | A | PART |
Troy Cobbley
|
|
|
Hydro test passed. KR
|
INSP-Sprinkler Rough-in | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | FAIL |
Troy Cobbley
|
|
|
Two arm overs more than 24 inches, see plans for details.KR
|