INSP-Final Inspection | 5/28/2008 | 5/29/2008 | 5/29/2008 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers for shell completed.KR
|
INSP-Final Inspection | 5/27/2008 | 5/28/2008 | 5/28/2008 | A | FAIL |
Troy Cobbley
|
|
|
Fire sprinkler testing complete ecept for bad flow switch. Will call in for re-test. KR
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2008 | 4/4/2008 | 4/4/2008 | P | PASS |
Troy Cobbley
|
|
|
Wet system hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/3/2008 | 4/3/2008 | 4/3/2008 | P | PART |
Troy Cobbley
|
|
|
The anti-freeze system hydro test passed. The fdc and wet system hydro tests failed.
|
INSP-Sprinkler Rough-in | 3/27/2008 | 3/28/2008 | 3/28/2008 | A | PASS |
Troy Cobbley
|
|
|
The tenting has been repaired and the piping can be covered.
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 | A | FAIL |
Troy Cobbley
|
|
|
The tenting is still inadequate. There are locations where the piping is not covered.
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/26/2008 | 3/26/2008 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was for the tenting which was not finished and/or lacking in many locations.
|
INSP-Sprinkler Rough-in/Hydro | 3/7/2008 | 3/7/2008 | 3/7/2008 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in is passed. Will need a tenting inspection for the wet system prior to cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/14/2008 | 2/15/2008 | 2/15/2008 | A | PASS |
Troy Cobbley
|
|
|
underground hydro and flush passed
|
INSP-Sprinkler Rough-in | 12/14/2007 | 12/14/2007 | 12/14/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground sprinkler piping is ok to cover
|