Permit Information
Permit NumberFIR07-00949
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 1655 S VINNELL ST
Project Name 
Customer Number 
ePlanReview 
Description
overhead & undergroundScope of Work: Overhead
The Underground scope of work includes connecting to an existing 6” C-900 capped line located at the property line, which was provided by others. (United Water) From there run 141’-0” out and up into the 1 hour rated riser room within a new 5,250-ft/2 bldg. The overhead fire sprinkler scope of work includes installing a 4” reduced pressure back flow device & wet riser. A wet tree system will serve through below the ceiling. An antifreeze system will serve the cold attic space and the exterior of the main entry way. The anti-freeze system will be a grid type system. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-02677.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/28/20085/29/20085/29/2008PPASS
DetailsTroy Cobbley
Fire sprinklers for shell completed.KR
INSP-Final Inspection5/27/20085/28/20085/28/2008AFAIL
DetailsTroy Cobbley
Fire sprinkler testing complete ecept for bad flow switch. Will call in for re-test. KR
INSP-Sprinkler Rough-in/Hydro4/4/20084/4/20084/4/2008PPASS
DetailsTroy Cobbley
Wet system hydro test passed.
INSP-Sprinkler Rough-in/Hydro4/3/20084/3/20084/3/2008PPART
DetailsTroy Cobbley
The anti-freeze system hydro test passed. The fdc and wet system hydro tests failed.
INSP-Sprinkler Rough-in3/27/20083/28/20083/28/2008APASS
DetailsTroy Cobbley
The tenting has been repaired and the piping can be covered.
INSP-Sprinkler Rough-in3/26/20083/27/20083/27/2008AFAIL
DetailsTroy Cobbley
The tenting is still inadequate. There are locations where the piping is not covered.
INSP-Sprinkler Rough-in3/26/20083/26/20083/26/2008PFAIL
DetailsTroy Cobbley
This inspection was for the tenting which was not finished and/or lacking in many locations.
INSP-Sprinkler Rough-in/Hydro3/7/20083/7/20083/7/2008PPASS
DetailsTroy Cobbley
Sprinkler rough-in is passed. Will need a tenting inspection for the wet system prior to cover.
INSP-Sprinkler Rough-in/Hydro2/14/20082/15/20082/15/2008APASS
DetailsTroy Cobbley
underground hydro and flush passed
INSP-Sprinkler Rough-in12/14/200712/14/200712/14/2007PPASS
DetailsTroy Cobbley
The underground sprinkler piping is ok to cover