INSP-Final Inspection | 1/29/2008 | 1/29/2008 | 1/29/2008 | P | PASS |
Forrest France
|
|
|
Permit finaled.
|
INSP-Final Inspection | 1/28/2008 | 1/28/2008 | 1/29/2008 | P | PASS |
Forrest France
|
|
|
Ceilings completed, permit okay for final.
|
INSP-Final Inspection | 1/18/2008 | 1/18/2008 | 1/18/2008 | P | CANC |
Forrest France
|
|
|
Overbooked, inspection rescheduled.
|
INSP-Final Inspection | 1/14/2008 | 1/15/2008 | 1/15/2008 | A | PART |
Forrest France
|
|
|
Fire sprinkler work passed for the north half of the permit area provided with hepa ceilings, verified main tie in, final pending remainder of ceiling installation.
|
INSP-Sprinkler Rough-in/Hydro | 1/4/2008 | 1/7/2008 | 1/7/2008 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new system piping passed, discussed project phase and final inspections.
|
INSP-Sprinkler Rough-in/Hydro | 1/3/2008 | 1/4/2008 | 1/4/2008 | A | PART |
Forrest France
|
|
|
Noted areas okayed for cover, minor field modifications to be reflected on as-built drawings, need to perform a hydrostatic test on the new system mains and branch lines, underfloor mods approved, discussed project phasing.
|