INSP-Final Inspection | 4/16/2010 | 4/16/2010 | 4/16/2010 | P | PASS |
Forrest France
|
|
|
Scope of fire sprinkler permit work finaled.
|
INSP-Final Inspection | 3/9/2010 | 3/9/2010 | 3/12/2010 | P | PART |
Forrest France
|
|
|
Scope of permit work appears satisfactory, however noted non-compliant spacing at an adjacent training room indicated as "OK" on plans.
|
INSP-Final Inspection | 12/18/2008 | 12/18/2008 | 12/18/2008 | A | NR |
Forrest France
|
|
|
Project is not ready for final at this time.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2008 | 10/29/2008 | 10/29/2008 | P | PART |
Forrest France
|
|
|
OH rough-in approved as noted on plans for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2008 | 5/5/2008 | 5/5/2008 | A | PART |
Forrest France
|
|
|
OH rough-in is approved for cover at the drop ceilings for the remainder of install as marked and initialed with today's date on approved plan set.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2008 | 5/2/2008 | 5/2/2008 | A | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 5/1/2008 at 12:02:49 PM. Contact: ###-####. Inspection rescheduled per phone conversation with contractor.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2008 | 3/4/2008 | 3/4/2008 | A | PART |
Forrest France
|
|
|
Fire sprinkler system modifications are approved for cover at the drop ceiling areas only as circled and initialed on plans with todays date, some rooms are not yet completed for inspection at this time.
|