INSP-Final Inspection | 6/11/2008 | 6/11/2008 | 6/11/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2008 | 5/14/2008 | 5/14/2008 | A | PASS |
Troy Cobbley
|
|
|
24 hr air test passed
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2008 | 4/30/2008 | 4/30/2008 | P | CANC |
Troy Cobbley
|
|
|
Jeremiah, please call 1 hr. prior; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
INSP-Sprinkler Rough-in | 2/29/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Troy Cobbley
|
|
|
The overhead sprinkler piping is ok to cover including the overbuilds.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2008 | 2/21/2008 | 2/21/2008 | A | PASS |
Troy Cobbley
|
|
|
The wet system hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2008 | 2/20/2008 | 2/20/2008 | P | PASS |
Troy Cobbley
|
|
|
All piping except the second floor is ok to cover. Brian Johnson needs to approve the new piping arrangement. The dry system hydro test passed. The wet system hydro test failed.
|