INSP-Final Inspection | 2/27/2008 | 2/29/2008 | 2/29/2008 | P | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 2/26/2008 | 2/27/2008 | 2/27/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic test for the east office area new branch lines and main passed inspection.
|
INSP-Sprinkler Rough-in | 2/18/2008 | 2/20/2008 | 2/20/2008 | P | PART |
Forrest France
|
|
|
See areas on approved plans okayed for cover, noted missing unistrut clamps at two locations on the 1 1/2 main, tie-in and EQ brace at the 2" main and 1 1/2 mains are not yet completed, need one upright installed at open office area south side, some noted items from previous inspection are finished, need to complete a hydrostatic test at the east office area new main and branch lines.
|
INSP-Sprinkler Rough-in | 2/13/2008 | 2/14/2008 | 2/14/2008 | A | PART |
Forrest France
|
|
|
See annotations on stamped plans for areas okayed for ceiling cover, noted seven heads at various locations that will need changed to QR, also noted obstructions to discharge at the server room, one painted ssu needs to be replaced.
|
INSP-Sprinkler Rough-in | 2/5/2008 | 2/6/2008 | 2/6/2008 | A | PART |
Forrest France
|
|
|
See approved plans for areas circled and initialed as okay for cover at the hard lid ceilings, be aware of possible light fixture obstructions due to surface mounted lights not installed at this time.
|
INSP-Sprinkler Rough-in | 2/4/2008 | 2/5/2008 | 2/5/2008 | P | CANC |
Forrest France
|
|
|
OH Cover Inspection
Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|