INSP-Final Inspection | 7/20/2008 | 7/21/2008 | 7/21/2008 | A | PASS |
Forrest France
|
|
|
Correction notice items are complete, final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 7/17/2008 | 7/18/2008 | 7/18/2008 | A | PART |
Forrest France
|
|
|
Need to provide matched temperature heads at the east mechanical room. Remainder of fire sprinkler work is acceptable and okay for final once correction is made.
|
INSP-Sprinkler Rough-in | 6/23/2008 | 6/24/2008 | 6/24/2008 | A | PART |
Forrest France
|
|
|
Overhead rough-in is okay for cover at the drop ceilings, verified corrections, one head at the OTS mech. room east side remains to be relocated.
|
INSP-Sprinkler Rough-in | 6/18/2008 | 6/19/2008 | 6/19/2008 | P | FAIL |
Forrest France
|
|
|
Armover hangers at several locations do not meet requirements of NFPA 13 2007 9.2.3.5.2.1, two heads adjacent to a continuous ceiling obstruction do not meet table 8.6.5.1.2, missing one head per drawings not installed, noted overspaced heads at four locations including a small room and open office areas, heads at an east side OTS room need relocated to avoid obstructions and meet head listing, overhead install is not approved for cover at this time.
|
INSP-Sprinkler Rough-in | 5/1/2008 | 5/2/2008 | 5/2/2008 | A | PART |
Forrest France
|
|
|
See approved plans for areas previously marked as okay for cover-no new hard lids to inspect at this time, new south entrance vestibule is not yet piped, be aware of possible obstructions/spacing issues at the front soffits depending on drop ceiling heights and head locations.
|
INSP-Sprinkler Rough-in | 4/21/2008 | 4/21/2008 | 4/22/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for new areas that are marked ok to cover.
|
INSP-Sprinkler Rough-in | 4/16/2008 | 4/16/2008 | 4/16/2008 | P | PART |
Forrest France
|
|
|
Okayed overhead rough-in at the hard lid ceilings as red lined with todays date on stamped plans.
|