Permit Information
Permit NumberFIR08-00109
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 190 E FRONT ST
Project NameCOURTHOUSE
Customer Number 
ePlanReview 
Description
This fire alarm permit is to upgrade the existing shell fire alarm system within the new TI area. Work includes new a/v notification appliances throughout the TI area, in-duct smoke detection actuation, new manual pull stations at two exits, and adding one new NAC panel and IDNET modules to the FAC Panel.

The associated building permit, BLD08-00102, is: ADA COUNTY - ASSESSORS OFFICE) To construct a core and shell and office build out for a 14,380 sq.ft. tenant space which includes minor interior demolition, replacing storefront doors with glazing and a new exterior entry vestibule and window decorative sunscreens per approved plans and DRH07-00359. Work includes construction of non-combustible fire-resistive wall partitions to create private offices, three distinct open office customer service and support areas, a break area, vault, file and conference areas; four fully accessible restrooms, drinking fountains and customer service counters; new suspended ceiling grid system and electrical, mechanical, plumbing, sprinkler and alarm system upgrades to meet tenant needs and provide code compliance. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/3/20087/3/20087/3/2008APASS
DetailsForrest France
C/N items are complete, final fire alarm test passed, permit finaled.
INSP-Final Inspection7/2/20087/2/20087/2/2008APART
DetailsForrest France
Nac, duct detectors, ID detectors, notification and initiation devices tested today throughout the tenant improvement area, noted one obstructed a/v at the file storage area (see plan review annotation), missing junction box cover above the nac panel, signals verified okay, final pending file room coverage adjustments and NFPA 72 forms for signature.
INSP-Final Inspection7/1/20087/1/20087/2/2008PDEFR
DetailsForrest France
Scheduled by a contractor via Hello! on 7/1/2008 at 7:55:22 AM. Contact: ###-####.
INSP-Conference3/25/20083/25/20083/25/2008PDONE
DetailsForrest France
Regarding field modifications not reflected on stamped plan set.