Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberFIR08-00113
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 398 S 9TH ST Unit: 270
Project NameBODO BLDG #4
Customer Number 
ePlanReview 
Description
overhead Work Scope:
(KOWALIS & MACKEY - BODO BLDG #4 - STE 270) This building is fully sprinklered for allowable area increase. To build out a SHELL & core area of 1,529 sq. ft. on the second floor for office use. Work include interior non-combustible wall framing, finishes, millwork, electrical, mechanical, sprinkler and alarm systems installation and a suspended ceiling grid system, all per approved plans, notes and attachments of all reviewing agencies.
The Fire Sprinkler scope consists of adding 84 new down heads and relocating 10 other up-right heads to accommodate a new wall and ceiling layout. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-03236 which is limited to suite 270.
When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verificatio
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/31/20083/31/20083/31/2008PPASS
DetailsForrest France
INSP-Final Inspection3/31/20083/31/20083/31/2008APASS
DetailsForrest France
Changes made per notes of Forrest last inspection.KR
INSP-Final Inspection3/28/20083/28/20083/28/2008PCANC
DetailsForrest France
final Inspection Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
INSP-Final Inspection3/27/20083/27/20083/27/2008PFAIL
DetailsForrest France
Need to relocate the pendent head at the north utility room due to cabinet obstruction.
INSP-Sprinkler Rough-in3/19/20083/20/20083/20/2008APART
DetailsForrest France
Overhead fire sprinkler rough-in is approved for cover at the drop ceilings as noted on plans.
INSP-Sprinkler Rough-in3/6/20083/7/20083/7/2008PPART
DetailsForrest France
See areas on approved plans marked with today's date for rough-in locations good for cover.
INSP-Sprinkler Rough-in2/25/20082/26/20082/26/2008APART
DetailsForrest France
Fire sprinkler rough-in is good for cover at the hard lid ceiling areas as red lined on approved plan set.