INSP-Final Inspection | 9/24/2008 | 9/25/2008 | 9/25/2008 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Final Inspection | 9/23/2008 | 9/24/2008 | 9/24/2008 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled with the fire alarm testing.
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2008 | 9/24/2008 | 9/23/2008 | A | CANC |
Forrest France
|
|
|
Final Inspection - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2008 | 8/15/2008 | 8/15/2008 | P | PASS |
Troy Cobbley
|
|
|
UG Flush Test passed
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2008 | 8/14/2008 | 8/14/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2008 | 5/8/2008 | 5/8/2008 | A | PASS |
Troy Cobbley
|
|
|
UG Cover Inspection passed. The underground piping as installed does not match the quick permit plan. The two 8" 45's have been removed and the underground now is run straight from the street to the riser room with no direction changes. I markded the permit plans and signed and dated them.
|