INSP-Final Inspection | 12/24/2008 | 12/29/2008 | 12/29/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | PART |
Forrest France
|
|
|
Functionality testing of the new and existing preaction risers completed today, PIV tamper at the west side needs adjustment, outside bell is not operational at the east side risers.
|
INSP-Final Inspection | 12/17/2008 | 12/19/2008 | 12/19/2008 | A | CANC |
Troy Cobbley
|
|
|
Russ Phone #: ###-####
|
INSP-Sprinkler Rough-in | 11/5/2008 | 11/6/2008 | 11/6/2008 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for areas where the sprinkler piping can be installed.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Troy Cobbley
|
|
|
See approved plans for areas where the sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/1/2008 | 10/2/2008 | 10/2/2008 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed for both systems
|
INSP-Sprinkler Rough-in | 9/30/2008 | 10/1/2008 | 10/1/2008 | A | DONE |
Troy Cobbley
|
|
|
Start of the 24 hour air test with 41.5 psi on the left system riser and 43 psi on the right system riser.
|
INSP-Sprinkler Rough-in/Hydro | 9/29/2008 | 9/30/2008 | 9/30/2008 | A | PASS |
Troy Cobbley
|
|
|
The piping to three additional pendant heads, as marked on the plans, is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2008 | 9/29/2008 | 9/29/2008 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed for both systems.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2008 | 9/17/2008 | 9/17/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2008 | 8/5/2008 | 8/5/2008 | A | PART |
Troy Cobbley
|
|
|
The rough-in inspection is passed. None of the arm-overs have been installed yet and will require an additional rough-in inspection to verify hangers for the arm-overs.
|