INSP-Final Inspection | 8/21/2008 | 8/21/2008 | 8/21/2008 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/13/2008 | 8/14/2008 | 8/14/2008 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Sam Rogers permission until the revised fire alarm plans showing the additional NAC panel have been approved and a field inspection verifies compliance with the new drawings. I tested the new NAC panel and it functioned correctly.
|
INSP-Final Inspection | 8/8/2008 | 8/8/2008 | 8/8/2008 | P | FAIL |
Troy Cobbley
|
|
|
Will be ready to final when all of the ceiling tile is installed.
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2008 | 8/6/2008 | 8/6/2008 | A | PASS |
Troy Cobbley
|
|
|
The remaining second floor rooms at the elevator are ok to cover.
|
INSP-Final Inspection | 8/5/2008 | 8/6/2008 | 8/6/2008 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for final inspection
|
INSP-Sprinkler Rough-in | 7/30/2008 | 7/31/2008 | 7/31/2008 | A | PASS |
Troy Cobbley
|
|
|
The remaining piping on the second floor is ok to cover except for the two rooms immediately adjacent to the elevator. The hydro test passed as well.
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2008 | 7/16/2008 | 7/16/2008 | P | PASS |
Troy Cobbley
|
|
|
Hydro Inspection of the first floor and the remaining first floor sprinkler piping is ok to cover. The second floor needs to be completed.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/14/2008 | 7/14/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the rooms where the sprinkler piping can be covered.
|