INSP-Final Inspection | 8/21/2008 | 8/21/2008 | 8/21/2008 | P | PASS |
Forrest France
|
|
|
Sprinkler inspection finaled. KR
|
INSP-Final Inspection | 8/19/2008 | 8/20/2008 | 8/20/2008 | P | FAIL |
Forrest France
|
|
|
Ceiling tiles removed for other work in progress. KR
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2008 | 8/20/2008 | 8/20/2008 | P | CANC |
Forrest France
|
|
|
Need an UG Hydro, Josh is the contact. Thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus NOTE: There is no underground work associated with this permit number.
|
INSP-Final Inspection | 8/15/2008 | 8/15/2008 | 8/15/2008 | A | PART |
Forrest France
|
|
|
Final pending ceiling tile and escutcheons.
|
INSP-Final Inspection | 8/13/2008 | 8/14/2008 | 8/14/2008 | P | FAIL |
Forrest France
|
|
|
Missing ceiling tile and escutcheons at all sprinkler head locations in the grid ceilings.
|
INSP-Sprinkler Rough-in | 8/7/2008 | 8/8/2008 | 8/8/2008 | A | PART |
Forrest France
|
|
|
Items on correction notice are finished, overhead fire sprinkler system modifications are okay for cover at the drop ceilings.
|
INSP-Sprinkler Rough-in/Hydro | 8/4/2008 | 8/5/2008 | 8/5/2008 | A | CANC |
Forrest France
|
|
|
Wrong permit number requested for inspection, was intended for a different project.
|
INSP-Sprinkler Rough-in | 7/30/2008 | 7/30/2008 | 7/30/2008 | P | FAIL |
Forrest France
|
|
|
See approved plans for necessary corrections including six pendent heads which exceed min. separation, and hangers at three locations missing correct retaining strap attatchments.
|