INSP-Final Inspection | 12/31/2008 | 12/31/2008 | 12/31/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit okay for final.
|
INSP-Final Inspection | 9/30/2008 | 9/30/2008 | 9/30/2008 | P | PART |
Forrest France
|
|
|
Correction notice items verified for completion, final pending field ceiling tile at conference rooms on the 4th, 5th and 6th floors.
|
INSP-Final Inspection | 9/29/2008 | 9/29/2008 | 9/29/2008 | P | FAIL |
Forrest France
|
|
|
Final pending installation of five missing escutcheons at the 6th floor, replace one damaged pendent head on the 4th floor, replace one painted head at the 4th floor, missing field tile at several rooms on 4th, 5th and 6th floors.
|
INSP-Final Inspection | 9/26/2008 | 9/26/2008 | 9/26/2008 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was for the 4th and 5th floors. Replace the painted sprinkler heads on the 5th floor, provide the missing canopies for all of the heads on the 4th and 5th floors, remove the "tin foil" from the heads on the 4th and 5th floors
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2008 | 9/18/2008 | 9/19/2008 | P | PART |
Forrest France
|
|
|
5th floor overhead rough-in at the grid ceilings is approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/17/2008 | 9/17/2008 | 9/17/2008 | P | FAIL |
Forrest France
|
|
|
5th floor overhead cover is not approved at this time due to painted upright heads at several locations, noted one missing head and one overspaced head at the 6th floor-see plans for locations.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2008 | 9/15/2008 | 9/15/2008 | A | PART |
Forrest France
|
|
|
4th floor overhead fire sprinkler work is approved for cover at the drop ceilings.
|
INSP-Sprinkler Rough-in/Hydro | 9/4/2008 | 9/5/2008 | 9/5/2008 | A | PART |
Troy Cobbley
|
|
|
Rough In 4th Floor is passed but the sprinkler piping can not be covered until the tape has been removed from the existing sprig-ups. Also see the city approved plans for a location where an additional upright is required due to a full height wall.
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2008 | 8/27/2008 | 8/27/2008 | A | PART |
Forrest France
|
|
|
Okayed work above sheetrock ceilings and soffits for the 6th floor-noted three heads in hard lids not yet finished, piping to be installed per plan at grid ceilings.
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2008 | 8/19/2008 | 8/19/2008 | P | PART |
Forrest France
|
|
|
OH install at the restroom, lounge and elevator lobby sheetrock lid ceilings is okay for cover, one head in a wall to be relocated, pendent heads at hard lid soffits are okay pending two heads supplied by a single one inch outlet is approved.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2008 | 8/15/2008 | 8/15/2008 | A | PART |
Forrest France
|
|
|
See plans for areas okayed to cover at the 4th floor.
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2008 | 8/14/2008 | 8/14/2008 | A | PART |
Forrest France
|
|
|
Inspection for the 4th floor hard lid areas and soffits completed today-okayed for cover at these locations only. Noted blocked upright protection at the NE corner of the reception room-see annotations on approved plan set.
|