INSP-Final Inspection | 11/25/2008 | 11/26/2008 | 11/26/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 11/5/2008 | 11/6/2008 | 11/6/2008 | A | FAIL |
Troy Cobbley
|
|
|
All items have been corrected except for the insulation is still causing obstructions to the upright sprinkler protection. I stopped at the project twice today.
|
INSP-Sprinkler Rough-in/Hydro | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PART |
Troy Cobbley
|
|
|
The sprinkler rough-in in general is ok. I need one painted head changed out and access provided above a storage room to verify upright sprinkler coverage. A separation needs to be provided between the area on the first floor where pendants were removed and uprights added and the phase two area that only has pendant protection. Also there are many locations where the second floor insulation is causing obstructions with the upright sprinkler heads.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2008 | 9/11/2008 | 9/11/2008 | A | FAIL |
Troy Cobbley
|
|
|
This inspection was for the cover of the piping above the restrooms on the second floor. The piping can not be covered until the existing insulation is re-attached to the roof deck and sprinkler protection is provided in the pipe chase between the two restrooms. I also spoke to Todd about resubmittals showing all of the additional upright heads addded due to full height walls.
|