Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR08-00563
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 400 N BENJAMIN LN
Project Name BENJAMIN CAMPUS
Customer Number 
ePlanReview 
Description
11/03/08 Revised Original FIR Work Scope:
The Fire Sprinkler scope was modified during construction to include the addition of 15 upright heads on the first and 45 other upright heads on the second levels above the ceiling as required. The maximum head spacing allowed shall not exceed 120-ft/2. The revision was noted as Rev #1 and dated 10/28/08. This modification does not appear to adversely affect the operation of the system FIR Work Scope: The Fire Sprinkler scope consists of adding 38 and relocating 211 other down head on the first & second floors to accommodate a new wall & ceiling layout. The contractor will also remove and plug 61 additional heads where required in the Microfilm file room ands various other locations. This modification does not appear to adversely affect the operation of the system The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD08-01168.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/25/200811/26/200811/26/2008APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro11/5/200811/6/200811/6/2008AFAIL
DetailsTroy Cobbley
All items have been corrected except for the insulation is still causing obstructions to the upright sprinkler protection. I stopped at the project twice today.
INSP-Sprinkler Rough-in/Hydro11/4/200811/5/200811/5/2008APART
DetailsTroy Cobbley
The sprinkler rough-in in general is ok. I need one painted head changed out and access provided above a storage room to verify upright sprinkler coverage. A separation needs to be provided between the area on the first floor where pendants were removed and uprights added and the phase two area that only has pendant protection. Also there are many locations where the second floor insulation is causing obstructions with the upright sprinkler heads.
INSP-Sprinkler Rough-in/Hydro9/10/20089/11/20089/11/2008AFAIL
DetailsTroy Cobbley
This inspection was for the cover of the piping above the restrooms on the second floor. The piping can not be covered until the existing insulation is re-attached to the roof deck and sprinkler protection is provided in the pipe chase between the two restrooms. I also spoke to Todd about resubmittals showing all of the additional upright heads addded due to full height walls.