INSP-Final Inspection | 11/25/2008 | 11/26/2008 | 11/26/2008 | A | PASS |
Forrest France
|
|
|
Final fire sprinkler permit inspection passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2008 | 11/25/2008 | 11/25/2008 | A | PART |
Forrest France
|
|
|
Pump acceptance testing completed satisfactory per NFPA 20 guidelines.
|
INSP-Sprinkler Rough-in/Hydro | 11/25/2008 | 11/25/2008 | 11/25/2008 | P | PART |
Forrest France
|
|
|
Hydrostatic re-test of overhead systems #3 and #5 passed.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2008 | 11/24/2008 | 11/24/2008 | A | PART |
Troy Cobbley
|
|
|
Above ground hydro tests of system 1, 2, 4 and 6 passed. System 3 and 5 failed. Also per NFPA 20 the suction and discharge on the fire pump needs to be hydro tested. The header and FDC had not been tested yet.
|
INSP-Sprinkler Rough-in/Hydro | 11/17/2008 | 11/18/2008 | 11/18/2008 | A | PART |
Forrest France
|
|
|
Overhead rough-in installation for warehouse systems #1 thru 6 passed inspection, noted riser and pump equipment not yet completed, discussed hydro test and pump acceptance schedule.
|