INSP-Final Inspection | 2/9/2009 | 2/9/2009 | 2/9/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/6/2009 | 2/6/2009 | 2/6/2009 | P | FAIL |
Troy Cobbley
|
|
|
Not all of the sprinkler work is complete. Forward flush passed. Tim Frost is ok with the relocation of the PIV from the landscape/island to the exterior wall. The electric alarm bell is missing.
|
INSP-Sprinkler Rough-in | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Troy Cobbley
|
|
|
The remaining piping can be covered. I noted one sprinkler pendant at the intermediate stair landing is overspaced from the north wall. Also per the builder insulation will be utilized above the ceiling in front of the public restrooms.
|
INSP-Sprinkler Rough-in | 1/6/2009 | 1/6/2009 | 1/7/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the hardlid soffits is ok to cover. I spoke to Brian Johnson and to Andy, the builder, about the PIV that was shown to be installed on the overhead sprinkler plans has not been installed. Per the separate underground permit FIR08-00514 no PIV was being installed. The PIV needs to be installed, a wall PIV approved by the city of boise installed or the one hour room with exterior access provided. Brian stated that he would contact me with a solution.
|
INSP-Sprinkler Rough-in/Hydro | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | PART |
Forrest France
|
|
|
Fire sprinkler piping at both the womens and mens restrooms only are approved for cover at this time.
|