Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR08-00831
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 4906 N CLOVERDALE RD
Project NameBoise Retirement Residence
Customer NumberBLDG B
ePlanReview 
Description
The Fire Sprinkler Scope of work consists of a new NFPA 13 fire protection system for BLDG B - East Section. This review is for Bldg B - East Section ONLY. A&C section will follow at a later date. (BOISE RETIREMENT RESIDENCE - BLDG B - EAST SECTION) To construct a new 60 unit 44,546 square foot, three story, I-1, non state licensed, residential care assisted, living facility, where all residence will be capable of responding to an emergency situation without physical assistance. This building to be fully fire sprinklered with an NFPA 13 system for area increase. This area is separated from the center building (Section A) by a 2-hr. fire wall. Note: This project was reviewed by ICC for energy, structural, nonstructural and accessibility requirements for code compliance. (52 units less than 800 sq.ft. and 8 units more than 800 sq.ft.)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/30/200910/1/200910/1/2009APASS
DetailsTroy Cobbley
permit finaled
INSP-Sprinkler Rough-in/Hydro9/16/20099/17/20099/17/2009APART
DetailsForrest France
Dry system hydrostatic test at building B manifold completed acceptable.
INSP-Sprinkler Rough-in9/10/20099/10/20099/11/2009PPASS
DetailsTroy Cobbley
This turned into a conference on what was left to complete on this project.
INSP-Final Inspection8/24/20098/25/20098/25/2009AFAIL
DetailsTroy Cobbley
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
INSP-Final Inspection8/5/20098/5/20098/5/2009PFAIL
DetailsTroy Cobbley
Todays inspection was for completed work in this building. The first and second floor is complete except for the corridors.
INSP-Sprinkler Rough-in8/4/20098/5/20098/4/2009ACANC
DetailsTroy Cobbley
Duplicate inspection.
INSP-Sprinkler Rough-in8/4/20098/4/20098/4/2009PPASS
DetailsTroy Cobbley
Todays inspection was for the third floor of this building which is complete as far as sprinkler head installation.
INSP-Sprinkler Rough-in/Hydro4/29/20094/29/20094/29/2009PPASS
DetailsTroy Cobbley
The first floor building "B" sprinkler piping can be covered.
INSP-Sprinkler Rough-in/Hydro4/15/20094/17/20094/17/2009APASS
DetailsTroy Cobbley
All sprinkler piping on teh second floor can be covered. As-built drawings were provided for the new piping in the overbuild areas and were signed and dated but will need to be submitted to the paln reviewer for approval.
INSP-Sprinkler Rough-in/Hydro4/6/20094/7/20094/7/2009APASS
DetailsTroy Cobbley
The sprinkler piping in the 3rd floor walls of building B is ok to cover. The insulation has been placed between the piping and the exterior wall.
INSP-Sprinkler Rough-in/Hydro3/23/20093/24/20093/24/2009APASS
DetailsTroy Cobbley
The rough-in piping for the second floor of building "B" is passed. A second inspection will be required for the insulation prior to cover.
INSP-Sprinkler Rough-in3/23/20093/23/20093/23/2009PPASS
DetailsTroy Cobbley
The rough-in for the third floor sprinkler piping passed. This includes the supply piping that is located on the second floor and the rise ups to the third floor. I found one piece of pipe that has been installed the wrong size and its location has been noted on the plans.
INSP-Sprinkler Rough-in/Hydro3/19/20093/23/20093/23/2009APASS
DetailsTroy Cobbley
The sprinkler piping rough-in for the first floor residential rooms of building "B" is passed. I noted one pendant head in the far south east corner resident room is overspaced. A second inspection will be required prior to a cover approval for the installation of the insulation.
INSP-Sprinkler Rough-in/Hydro2/24/20092/24/20092/24/2009PPASS
DetailsTroy Cobbley
1st Floor North Corridor Bldg B - Ok to cover
2nd Floor Bldg B Corridor - Ok to Cover

Told the fire protection contractor and general contractor that the same type of insulation arrangement would not be adequate in the rooms since the composite wood joist were deeper. The corridor joist space was almost entirely filled with insulation. In addition, the corridor joist space were much less than the 160^3 defined in NFPA 13
INSP-Sprinkler Rough-in/Hydro2/11/20092/12/20092/12/2009APASS
DetailsTroy Cobbley
The B wing second floor corridor branchline piping rough-in passed. A separate cover inspection will be required once the insulation is installed.
INSP-Sprinkler Rough-in/Hydro2/6/20092/9/20092/9/2009PPASS
DetailsTroy Cobbley
The sprinkler piping located in the first floor B wing corridor above the sheet rock can be covered.