INSP-Final Inspection | 9/30/2009 | 10/1/2009 | 10/1/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 9/16/2009 | 9/17/2009 | 9/17/2009 | A | PART |
Forrest France
|
|
|
Dry system hydrostatic test at building B manifold completed acceptable.
|
INSP-Sprinkler Rough-in | 9/10/2009 | 9/10/2009 | 9/11/2009 | P | PASS |
Troy Cobbley
|
|
|
This turned into a conference on what was left to complete on this project.
|
INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
|
INSP-Final Inspection | 8/5/2009 | 8/5/2009 | 8/5/2009 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for completed work in this building. The first and second floor is complete except for the corridors.
|
INSP-Sprinkler Rough-in | 8/4/2009 | 8/5/2009 | 8/4/2009 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection.
|
INSP-Sprinkler Rough-in | 8/4/2009 | 8/4/2009 | 8/4/2009 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was for the third floor of this building which is complete as far as sprinkler head installation.
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2009 | 4/29/2009 | 4/29/2009 | P | PASS |
Troy Cobbley
|
|
|
The first floor building "B" sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 4/15/2009 | 4/17/2009 | 4/17/2009 | A | PASS |
Troy Cobbley
|
|
|
All sprinkler piping on teh second floor can be covered. As-built drawings were provided for the new piping in the overbuild areas and were signed and dated but will need to be submitted to the paln reviewer for approval.
|
INSP-Sprinkler Rough-in/Hydro | 4/6/2009 | 4/7/2009 | 4/7/2009 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the 3rd floor walls of building B is ok to cover. The insulation has been placed between the piping and the exterior wall.
|
INSP-Sprinkler Rough-in/Hydro | 3/23/2009 | 3/24/2009 | 3/24/2009 | A | PASS |
Troy Cobbley
|
|
|
The rough-in piping for the second floor of building "B" is passed. A second inspection will be required for the insulation prior to cover.
|
INSP-Sprinkler Rough-in | 3/23/2009 | 3/23/2009 | 3/23/2009 | P | PASS |
Troy Cobbley
|
|
|
The rough-in for the third floor sprinkler piping passed. This includes the supply piping that is located on the second floor and the rise ups to the third floor. I found one piece of pipe that has been installed the wrong size and its location has been noted on the plans.
|
INSP-Sprinkler Rough-in/Hydro | 3/19/2009 | 3/23/2009 | 3/23/2009 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping rough-in for the first floor residential rooms of building "B" is passed. I noted one pendant head in the far south east corner resident room is overspaced. A second inspection will be required prior to a cover approval for the installation of the insulation.
|
INSP-Sprinkler Rough-in/Hydro | 2/24/2009 | 2/24/2009 | 2/24/2009 | P | PASS |
Troy Cobbley
|
|
|
1st Floor North Corridor Bldg B - Ok to cover 2nd Floor Bldg B Corridor - Ok to Cover
Told the fire protection contractor and general contractor that the same type of insulation arrangement would not be adequate in the rooms since the composite wood joist were deeper. The corridor joist space was almost entirely filled with insulation. In addition, the corridor joist space were much less than the 160^3 defined in NFPA 13
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2009 | 2/12/2009 | 2/12/2009 | A | PASS |
Troy Cobbley
|
|
|
The B wing second floor corridor branchline piping rough-in passed. A separate cover inspection will be required once the insulation is installed.
|
INSP-Sprinkler Rough-in/Hydro | 2/6/2009 | 2/9/2009 | 2/9/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping located in the first floor B wing corridor above the sheet rock can be covered.
|