Permit Information
Permit NumberFIR08-00832
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 4892 N CLOVERDALE RD
Project NameBoise Retirement Residence
Customer NumberBLDG C (EAST)
ePlanReview 
Description
(BOISE RETIREMENT RESIDENCE - BLDG C - WEST SECTION) To construct a new 29 unit 23,254 square foot, three story, I-1, non state licensed, residential care, assisted living facility where all residence will be capable of responding to an emergency situation without physical assistance. This building to be fully fire sprinklered with an NFPA 13-R system as required by the occupancy. This area is separated from the center building (Section A) by a 2-hr. fire wall. Note: This project was reviewed by ICC for energy, structural, nonstructural and accessibility requirements for code compliance. (23 units are less than 800 sq.ft. and 6 units are greater than 800 sq.ft.)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/30/200910/1/200910/1/2009APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection8/24/20098/25/20098/25/2009AFAIL
DetailsTroy Cobbley
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
INSP-Final Inspection8/6/20098/6/20098/6/2009PFAIL
DetailsTroy Cobbley
Todays inspection was for work completed on the first floor residence rooms, which all are. The corridors are not yet complete.
INSP-Final Inspection8/5/20098/5/20098/5/2009PFAIL
DetailsTroy Cobbley
Todays inspection was for completed work in this building. Everything is complete on the second floor except for the corridor.
INSP-Final Inspection8/4/20098/4/20098/4/2009PFAIL
DetailsTroy Cobbley
Todays inspection was for the third floor of this building which is complete as far as sprinkler head installation.
INSP-Sprinkler Rough-in/Hydro5/26/20095/27/20095/27/2009APASS
DetailsTroy Cobbley
The first floor of Building C sprinkler piping can be covered with sheet rock. The insulation has been installed.
INSP-Sprinkler Rough-in/Hydro5/18/20095/20/20095/20/2009PPASS
DetailsTroy Cobbley
The insulation has been installed on the second floor of building C and can be covered with sheet rock. I notified Mike, the superintendant.
INSP-Sprinkler Rough-in/Hydro5/14/20095/15/20095/14/2009APASS
DetailsTroy Cobbley
All of the sprinkler piping in building C can be covered with sheet rock. Insulation was verified behind the vertical risers in the exterior walls.
INSP-Sprinkler Rough-in/Hydro4/29/20095/1/20095/1/2009APASS
DetailsTroy Cobbley
The sheet rock can be installed on the bottom of the trusses in the 1st, 2nd and 3rd floor corridors of building "C"
INSP-Sprinkler Rough-in/Hydro4/28/20094/29/20094/29/2009APART
DetailsTroy Cobbley
Todays inspection was for the third floor piping of building "C". The pipe size and hangers are passed. Another inspection will be required prior to cover for the insulation.
INSP-Sprinkler Rough-in/Hydro4/27/20094/28/20094/28/2009APART
DetailsTroy Cobbley
Todays inspection covered building "C" first and second floors. The sidewall sprinkler heads provided under the exterior canopies are wrong and the correct ones will need to be installed. Pipe sizing and hangers appear to be correct. One additional sidewall has been added under a southwest exterior canopy. Sprinkler piping can't be covered until the insulation has been inspected. Also the pendant heads in the corridors have not been cut in yet.
INSP-Sprinkler Rough-in/Hydro4/24/20094/27/20094/27/2009PCANC
DetailsForrest France
Overbooked