INSP-Final Inspection | 9/30/2009 | 10/1/2009 | 10/1/2009 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 8/24/2009 | 8/25/2009 | 8/25/2009 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was a rough-in inspection for the first and second floor corridors where the piping is ok to cover. The central core areas still need to be completed on both floors.
|
INSP-Final Inspection | 8/6/2009 | 8/6/2009 | 8/6/2009 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for work completed on the first floor residence rooms, which all are. The corridors are not yet complete.
|
INSP-Final Inspection | 8/5/2009 | 8/5/2009 | 8/5/2009 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for completed work in this building. Everything is complete on the second floor except for the corridor.
|
INSP-Final Inspection | 8/4/2009 | 8/4/2009 | 8/4/2009 | P | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the third floor of this building which is complete as far as sprinkler head installation.
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2009 | 5/27/2009 | 5/27/2009 | A | PASS |
Troy Cobbley
|
|
|
The first floor of Building C sprinkler piping can be covered with sheet rock. The insulation has been installed.
|
INSP-Sprinkler Rough-in/Hydro | 5/18/2009 | 5/20/2009 | 5/20/2009 | P | PASS |
Troy Cobbley
|
|
|
The insulation has been installed on the second floor of building C and can be covered with sheet rock. I notified Mike, the superintendant.
|
INSP-Sprinkler Rough-in/Hydro | 5/14/2009 | 5/15/2009 | 5/14/2009 | A | PASS |
Troy Cobbley
|
|
|
All of the sprinkler piping in building C can be covered with sheet rock. Insulation was verified behind the vertical risers in the exterior walls.
|
INSP-Sprinkler Rough-in/Hydro | 4/29/2009 | 5/1/2009 | 5/1/2009 | A | PASS |
Troy Cobbley
|
|
|
The sheet rock can be installed on the bottom of the trusses in the 1st, 2nd and 3rd floor corridors of building "C"
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2009 | 4/29/2009 | 4/29/2009 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was for the third floor piping of building "C". The pipe size and hangers are passed. Another inspection will be required prior to cover for the insulation.
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2009 | 4/28/2009 | 4/28/2009 | A | PART |
Troy Cobbley
|
|
|
Todays inspection covered building "C" first and second floors. The sidewall sprinkler heads provided under the exterior canopies are wrong and the correct ones will need to be installed. Pipe sizing and hangers appear to be correct. One additional sidewall has been added under a southwest exterior canopy. Sprinkler piping can't be covered until the insulation has been inspected. Also the pendant heads in the corridors have not been cut in yet.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2009 | 4/27/2009 | 4/27/2009 | P | CANC |
Forrest France
|
|
|
Overbooked
|